Report for August 2013

Report Date
August 2013

Report compiled by Jamie Thin (IS Apps Programme Manager)

Section One: Programme Commentary, RAG and Resources Update

 

Work on DAS008 has been carried over to 13-14. Development and Alumni have requested that the project is suspended until Feb 2014.

--

 

 

 

 

 

 Section Two: Projects Not Started

 

None

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

RES049

 

Category: Core

Milestones

22-Nov-2013REF Freeze ends
06-Dec-2013Delivery: Completion of Bug fixes in lIve
20-Dec-2013DSOR
10-Jan-2014Closure

RAG Status

GREEN

Report for September 2013 by Sue Woodger

Achievements in Last Period

  • Planning milestone and project brief approved 6/9/13
  • Bug fixes sorted in Beta and test - will go into live after REF freeze :
    •  RES049-29 missing persons no PI Split

  • Bug fixes resolved

    • RES049-30, RES049-31, RES049-34: all about documentation - now on wiki

Issues

  • Ref freeze started 15 September so no fixes can go into live until the freeze ends

Next Steps for September

  • Continuation with fixing bugs in remaining jiras: RES049-15; RES049-38

 

Project is GREEN as plan available and on schedule

 

DAS008

Decommission Alumni Live Database

 

Category: Core

Milestones

 

   Target date         Title
Post SuspensionDeploy New ThankQ Feed to TEST
06-Sep-2013Deploy New Version of CCTS and Events booking to TEST
23-Sep-2013ASOR- CCTS and Event Booking
Post SuspensionASOR - ThankQ Feed
Post SuspensionDeploy New ThankQ Feed to LIVE
30-Sep-2013Deploy New Version of CCTS and Events Booking to LIVE
04-Oct-2013DSOR - CCTS and Events booking
Post SuspensionDSOR - ThankQ Feed
Post SuspensionComplete Decomission of ALUMLIVE Instances
Post SuspensionClosure

 

RAG Status

RED

Report for August 2013
  • Achievements in Last Period

Testing has completed successfully in IDM DEV

Work has completed in development to remove the Events Booking dependency on the ALUMLIVE Database.

A Test plan for IDM TEST has been devised with App Managemt and Service Management.

  • Issues

Resourcing is required for the MyEd portion. PM to discuss with Reource Managers

  • Next Steps

Complete testing in IDM TEST

Test and Deploy CCTS and Events Booking

Replan milestones accordingly and restimate current and new tasks.

Confirm external resources for next steps of project.

 

The ThankQ feed testing is now not expected to take place until March 2014 and the project will be suspended until the client Department can resource the testing.

 