Report for October 2013
- Report Date
- October 2013
Report compiled by Jamie Thin (IS Apps Programme Manager)
Section One: Programme Commentary, RAG and Resources Update
Work on DAS008 has been carried over to 13-14. Development and Alumni have requested that the project is suspended until Feb 2014.
--
Section Two: Projects Not Started
None
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||
RES049
Category: Core Milestones
RAG Status GREEN | Report for October 2013 by Sue Woodger
Achievements in Last Period
Issues
Next Steps for November
Project is GREEN as plan available and on schedule
| ||||||||||||||||||||
DAS008 Decommission Alumni Live Database
Category: Core Milestones Target date Title
RAG Status AMBER | Report for October 2013
Discussed and agreed approach and estimates to complete CCTS and Events Booking Changes with Development Services. Agreed dates with Business users for next stage of testing. Confirmed resources to deploy Events booking to TEST. Resourcing agreed to deploy
Potential resouce conflicts may continue on timetabling
Test and deploy CCTS and Events Booking to LIVE Monitor potential resource conflicts The plan to complete the Events Bookings and CCTS part of the project are to be resourced. |
Section Four: Closed or Withdrawn Projects
None