Report for March 2020
- Report Date
- March 2020
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge (USG), Kate Brook (D&A), Jenny Shaw (D&A), Rebecca Gaukroger (SRA), Gillian Simmons (SRA), and other interested business area owners.
Section One: Programme Commentary, RAG and Resources Update
Commentary
On 18 March, a new major issue arose, following the pandemic of Covid-19, everyone who can work from home is now working from home. After a period of transition where everyone move to home working, including external partners, work in our programme continue and projects are able the progress. Potential for other and additional issues continue to be monitored under Risk 2:Disruption from the current Novel coronavirus (Covid-19) outbreak.
During March, our yearly Clearing project started. However the Covid-19 outbreak will have a major impact on this project. The project scope is under review and will be adapted to follow the guidance from the government and the University Executive.
USG014 Development and Alumni CRM Procurement has moved to the evaluation stage. The timeline has been revised, but may be extended further on the advise of Procurement. This project will now continue into session 2020/21.
Both projects are reporting an AMBER status. As a result, the overall USG Other Programme status is AMBER.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - March 2020
Resources to end March 2020
The budget for session 2019/20 increased from 308 days to 352 days following return of days from HRS to the portfolio contingency , see PRICCL 122.
Section Two: Projects Not Started
There is no new project planned to start this session.
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||||
USG014 Development and Alumni CRM Procurement
Category: Discretionary
RAG StatusAMBER |
Report by Ben Armstrong for March 2020Achievements this period
Issues
Next Steps
|
||||||||||||||
Category: Discretionary
RAG StatusAMBER |
Report by Frankie Quinn for March 2020Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
USG012 ThankQ Infrastructure Upgrade | This project was started in August 2018 and was closed on 21 February 2020. The Closure Report is available to view. |
USG013 Clearing 2019 | This project was started in March 2019 and was closed on the 25 October 2019. The Closure Report is available to view. |