Report for August 2021

Report Date
August 2021

Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Jim McGeorge and Rena Gertz (USG), Edd McCracken (CAM), Rebecca Gaukroger and Gillian Simmons (SRA) and other interested business area owners.

 

Section One: Programme Commentary, RAG and Resources Update

Commentary

The new 2021/22 session starts with four ongoing projects. During August, USG017 Clearing 2021 was successfully delivered and is expected to close next month/

All projects are reporting a GREEN RAG status.

Therefore the overall USG Other Programme status is GREEN.

We continue to monitor the ongoing impact from Covid-19 outbreak and disruption from the current Novel coronavirus (Covid-19) outbreak.

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

 

Forward Look - August 2021

 

Resources to end August 2021

The programme budget at the start of the 21/22 session is 306 days, with 120 days of sponsor funding and 186 days of Core funding, see PRICLL 133. It includes 17 days of core funded contingency.

 

Section Two: Projects Not Started

Project Programme Manager's Commentary

USG020 Clearing 2022

This annual project is scheduled to start in March.

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

USG016 Signal to PURE Application

Category: Discretionary

 

Milestones

Target Date Title
13-Aug-2021 UAT Completion
27-Aug-2021 Delivery Sign Off
30-Aug-2021 Go Live
03-Sep-2021 Project Closure

 

RAG Status

GREEN

Report by Alan Donald for August 2021

Achievements

  • UAT progressed by CAM

Issues

  • Major issue preventing the import of data into PURE picked up in UAT
  • Developer had to take leave unexpectedly at short notice, back on 6th September

Next Steps

  • Complete UAT
  • Handover to Production
  • Close Project

USG017 Clearing 2021

Category: Compliance

 

Milestones

Target Date Title
30-Sep-2021 Project Closure
 
RAG Status

GREEN

Report by Susan Ridder-Patrick for August 2021

Achievements

  • Completion of physical set-up in Argyle House
  • Completion of telephone configuration and testing
  • Completion of operator training and guidance
  • Set-up of MS Group chats for use during Helpline opening hours
  • Successful running of Results Helpline on 10th-12th August
  • Call Centre closed down
  • Closure report and lessons learning drafted

Issues

  • Several issues were encountered with the physical set up of the training rooms in Argyle House and there were issues with the supplier's telephone configuration but these were all resolved in time through collaboration of ISG teams prioritising this project

Next Steps

  • Complete review of call centre usage with supplier
  • Complete Closure report and close project

USG018 Mapping International Data Transfer

Category: Compliance

 

Milestones (to be updated)

Target Date Title
13-Augl-2021 Survey end date
27-Aug-2021 Delivery of Project Outcomes
10-Sep-2021 Project Closure
 
RAG Status

GREEN

Report by Muriel Mewissen for August 2021

Achievements in last period

  • Survey deadline extended to 13 August, see change control 5.
  • Ongoing support of DPOs and survey respondents while survey is available
  • Regular checking and analysis of submissions
  • Chasing and prompting of areas with zero/low returns
  • Start work on analysis and report

Issues

  • No new issue

Next steps

  • Complete analysis and report
  • Write closure report
  • Close Project

USG019 Development & Alumni CRM deployment

Category: Discretionary

Milestones

 

Target Date Title
24-Sep-2021 Project Brief Approval
08-Oct-2021 Analysis & Design Approval
29-Oct-2021  Single Sign-on enabled
04-Nov-2021 Data migration 1 - complete
04-Feb-2022 Data migration 2 - complete
22-Feb-2022 Build review
11-Mar-2022 Penetration testing completed
06-May-2022 Integration & Acceptance Review
06-May-2022 Data migration 3 - complete
13-May-2022 Project Delivery
20-May-2022 Delivery Review
29-Jul-2022 Project Closure
RAG Status

GREEN

 

Report by Susan Ridder-Patrick for August 2021

Achievements

  • Series of meetings held with D&A and Supplier to scope out the project
  • Project brief drafted
  • Resource estimate to closure completed
  • Project resources requested in ASTA
  • EQiA reviewed and updated
  • MS Teams site set-up for project

Issues

  • Approval of brief was not achieved by 27th August and a change control is being processed to revise this to 24th September which will accommodate leave in September in D&A.
  • Project estimate is substantially over the allocation in the USG 21/22 plan. The project sponsor has secured the additional funding required.

Next Steps

  • Complete Project Brief approval
  • Obtain assignments for software development resource requests
  • Complete documentation of business requirements
  • Systems Design developed
Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No

Documentation

Not available.