August 2016
- Report Date
- August 2016
SMI Programme Report compiled by Colin Watt (IS Apps Programme Manager) for Programme Owners Bryan MacGregor and Alex Carter
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: AMBER
Overall, the programme is in Amber status with SMI008 and SMI013 closures outstanding.
Contingency has already been applied to manage unplanned carryover.
Forward Look and RAG
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP67-042 UniDesk Annual Upgrade | Scheduled start: February 2017. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
SMI008 (AP45-036) Improved Unidesk reporting Category: Discretionary
Milestones
RAG Status AMBER | Report by Colin Forrest for August 2016
Achievements in the last period
Issues
Next steps
| ||||||||||||||
UniDesk Annual Upgrade Category: Compliance Milestones
RAG Status AMBER | Report by Iain Moore-McLaughlin for August 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
UniDesk for new member Category: Discretionary Milestones
RAG Status GREEN Milestones RAG Status GREEN | Report by Iain Moore-McLaughlin for August 2016Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Digital Image Submissions for Staff and Visitors | Project Closure Approved 05/08/16 |