UniDesk Programme Report - February 2013
Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for UniDesk Project Board
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The ITS081 Change and Release project delivered on 7th March, so that C&R is now operational for Abertay, will be a limited release on v 4 for Edinburgh, and will launch on v 5 in St Andrews. This is in line with the planned delivery as directed by the Project Board in December.
The SMI002 UniDesk Upgrade also proceeding well - but revised estimates are projecting a significant increase in the effort required, and the project delivery has moved to the end of May/early June. This could impact on Edinburgh and St Andrews who wish to roll out C&R on v 5. Programme Manger will be meeting with the SMI002 project team to review the estimates and plan before Project Board meets. From both timings and the programme budget, CMDB can now start in 12/13 as had been hoped but there is a risk that it will have less days available in the current year.
Actions from programme meeting
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-047 CMDB Implementation Funded Approved funding 12/13 is 73 days (53 days for Applications) - thisdepends on previous projects being within budget. Milestones Spring 2013 Planning TBC Winter 2013 Delivery TBC
RAG Status AMBER | Plan The project board met on 31st August to review the proposed programme schedule for 2012/13 and 2013/14. CMDB has been pushed back into Spring 2013, and only if we had the days after the projects to upgrade TOPdesk to v 5 and the Unidesk C&R project are completed. The project is expected to get the go ahead at the March board meeting.
Dependencies None |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
ITS081 (AP01-926) Funded Approved funding for 12/13 is 47 days (31 days for Applications). Milestones
RAG Status GREEN | Report by Maurice Franceschi for February 2013
Achievements in Last Period
Issues No issues Next Steps Abertay will use C&R on v 4 St Andrews will use C&R on v 5 Edinburgh will roll out C&R on v 4 to a small group, then to the community on v 5 Project Engagement will be developed on v 5 Documentation will be updated by SMI002 Timetable for activities available from https://www.wiki.ed.ac.uk/display/ServManITIL/ITS081+Tasklist+and+Milestone | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
SMI002 (AP23-406) Funded Approved funding for 12/13 is 80 days (60 days for Applications). Milestones Current Milestones - need to be reviewed/restated by mid-March
RAG Status AMBER | Report by Sue Woodger for February 2013 Achievements in Last Period
Issues
Next Steps
Project is AMBER as revised project plan is not complete
|
Section Four: Projects Closed / Withdrawn
Project Info | Project Managers Commentary |
AP23-017 UniDesk Shared Service Patch Not Funded | Withdrawn. Work has been done under Service. |
Actions from October Programme Meeting (9th November)
Annual Planning to be approved by Project Board, but we propose CMDB carry over Card Reader, sponsored by Bryan, funding could be core or partners if not Edinburgh specific, small UPortal, sponsored by Bryan, core funding, Edinburgh specific, small | ||
Maurice and Stefan to meet with projects soon to discuss C&R | ||
Actions from September Programme Meeting (5th October)
Neil Bruce can be C&R Process Manager in UniDesk if Stefan or David cannot take on the role. | Bryan to dicuss with Neil - Maurice to confirm with Stefan and David Resolved - Robert Gormley
| |
The current unidesk user group would be a good forum to present C&R changes | Stuart to action | |
Actions from August Programme Meeting (14th September)
Set up meeting to discuss how to promote CABS | Maurice | Done |
C&R project will not set up CABS | Maurice | Done |
Get V 5 Upgrade project started asap | Maurice | Done |