UniDesk Programme Report - July 2013

 

Report compiled by Maurice Franceschi (IS Apps Programme Manager) for UniDesk Project Board

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects

 

Section One: Programme Commentary, RAG and Resources Update  

The SMI002 UniDesk Upgrade has upgraded TOPdesk in all four universities. Unfortunately, a conlfict from Finance on Peter Jackson  means the project has carrried over into 2013/14 to complete the documentation  before it can be closed.

The SMI003 CMDB project has had an initial workshop with our partners and TOPdesk, which has helped  to determine scope and timelines, and a project brief is now with partners to approve. There is now an projected overspend of 11 days on SMI002 - programme manager will discuss options with project manager, and review estimates for the SMI003 project to see if the overspend can be offset within the new 2013/14 funded programme budget.

 

 

Oustanding Actions from Programme Meetings

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary
All planned projects have started 

 

Section Three: Projects in Progress

Project InfoProject Managers Commentary

SMI003 (AP23-047)

UniDesk CMDB

Funded

Approved funding for 12/13 is 3 days (5 days for Service management). Approved funding for 13/14 is 105 days (45 days for Service management).  

Milestones

09-Aug-2013Project Brief
12-Dec-2013Delivery of CMDB Process and Configured Database

 

RAG Status

GREEN
 

Report by Maurice Franceschi for July 2013

 

Achievements in Last Period

  • none were planned
  • TOPdesk have set out a timeline of activities which are a good basis for the project plan
  • Project Brief and estimates agreed within Edinburgh and sent out to partners for approval by 9th August

Issues

No issues  

Next Steps  

Project Brief, Estimations and Planning

 

 

 

 

  

SMI002 (AP23-406)

TOPdesk Upgrade to v 5

Funded

Approved funding for 12/13 is 105 days (85 days for Applications) - approved 28 March 13.

Milestones

 

16-Aug-2013Deployment Sign-Off
20-Aug-2013Closure

 

 

 

 

RAG Status

BLUE

 

 

Report by Sue Woodger for July 2013

 

Achievements in Last Period

  • DR completed
  • Demo upgrade completed

 

Issues

  • Conflict with FIN084 has resulted in losing Peter Jackson's time to complete outstanding items for DSOR. Peter will however complete the following items at the beginning of his secondment to Production Management (12 August 13)
    • TAD
    • Operation document
    • Deletion of V4
    • There was an issue getting these tasks assigned as Production Mnagement couldnt do them  - Peter has to assign his own tasks

Next Steps

  • DSOR replanned for 16 August
  • Closure replanned for 20 August
 
A carry over of 5 days is estimated for SMI002 for 2013/14

 

 

 

 

Section Three: Closed/Withdrawn Projects

 

Project InfoProject Managers Commentary
  

AP23-017 UniDesk Shared Service Patch

Not Funded

Withdrawn. Work has been done under Service.

ITS081

UniDesk Change & Release

Funded

 

 

Closed

 

 