UniDesk Programme Report -March 2013
Report compiled by Maurice Franceschi (IS Apps Programme Manager) for UniDesk Project Board
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Project Board met on Monday 25th to review and decided on various issues.
The ITS081 Change and Release project has delivered, the configuration of the process on all Live environments has been signed off. Project Board have approved closure in April.
The SMI002 UniDesk Upgrade will deliver upgrades to the four universities between late May and late June, and has had its budget increased by 25 days with Board Approval.
As directed by the Project Board, The CMDB project will move to 2013/14, with a little exploratory work in June/July. This will be the only project for next year to be undertaken by the universities.
SLA and Service Delivery will be 14/15 projects.
However, the Card Integration work will go ahead, to be developed entirely by TOPdesk.
After the above changes, the programme budget which had been Baselined at 200 days in August is now reduced to160 days for 12/13.
Actions from programme meeting
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-047 CMDB Implementation Funded Approved funding 12/13 is 8 days Milestones Initial investiations, with TOPdesk and partners, scoping - June Project under way August
RAG Status AMBER | Plan The project board met on 25th March and decided that the CMDB project should move to 13/14, apart from a few days preliminary scoping before July.
Dependencies None |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
ITS081 (AP01-926) Funded Approved funding for 12/13 is 47 days. Milestones
RAG Status BLUE | Report by Maurice Franceschi for March 2013 C&R is now live, and is use at Abertay. Edinburgh will release to a limited group on v 4 of UniDesk.
Achievements in Last Period
IssuesNo issuesNext StepsClosure
Timetable for activities available from https://www.wiki.ed.ac.uk/display/ServManITIL/ITS081+Tasklist+and+Milestone | ||||||||||||
SMI002 (AP23-406) Funded Approved funding for 12/13 is 105 days - approved 25 March 13. Milestones
RAG Status GREEN
| Report by Sue Woodger for March 2013 Achievements in Last Period
Issues
Next Steps
Project is GREEN as revised project plan in place and revised funding approved
|
Section Four: Projects Closed / Withdrawn
Project Info | Project Managers Commentary |
AP23-017 UniDesk Shared Service Patch Not Funded | Withdrawn. Work has been done under Service. |
Actions from October Programme Meeting (9th November)
Annual Planning to be approved by Project Board, but we propose CMDB carry over Card Reader, sponsored by Bryan, funding could be core or partners if not Edinburgh specific, small UPortal, sponsored by Bryan, core funding, Edinburgh specific, small | Done | |
Maurice and Stefan to meet with projects soon to discuss C&R | Done | |
Actions from September Programme Meeting (5th October)
Neil Bruce can be C&R Process Manager in UniDesk if Stefan or David cannot take on the role. | Bryan to dicuss with Neil - Maurice to confirm with Stefan and David Resolved - Robert Gormley
| |
The current unidesk user group would be a good forum to present C&R changes | Stuart to action | |
Actions from August Programme Meeting (14th September)
Set up meeting to discuss how to promote CABS | Maurice | Done |
C&R project will not set up CABS | Maurice | Done |
Get V 5 Upgrade project started asap | Maurice | Done |