Report for February 2022

Report Date
February 2022

Section One: Programme Commentary, RAG and Resources Update

Commentary

Programme status: The overall status of the STU programme for February 2022 is AMBER due to Risk 14 noted below but also due to strike action which has impact STU267.

Risks

Risk 14: AMBER - Unresolved issues on how to replace legacy UG & PG Degree Finder application - issue escalated to USG and ISG senior leadership team. Current UG & PG  Degree finder tech stack is legacy end-of-life code , and will get very difficult to make any substantial changes going forward,  if there are any external statutory drivers for change

Project Highlights

  • STU265: GREEN - Delivery achieved and decommissioning work underway ahead of closure
  • STU267: AMBER - Delivery date at risk as industrial action has prevented full planning to be completed however progress was made outside of the technical work.

Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.

 

Forward Look - February 2022

Resources to end February 2022

Section Two: Projects Not Started

Project Programme Manager's Commentary
N/A Planned projects are in progress

Section Three: Projects in Progress

Project Info

Project Manager's Commentary

STU265 G-Cloud replacement of FOI Request planning tool

Category:  Compliance

 

  Export all milestones

Stage Milestone Due Date
Close Project Closure 18-Mar-2022
Deliver Legacy ColdFusion Decommissioned 18-Mar-2022

RAG Status - Green

 

Report by Alan Donald for February 2022

Achievements

  • Records Management agreed to decommission ColdFusion FOI system
  • Decommission process started
  • On-going support provided to Records Management team after the  eCase  go-live on 3rd March

Issues

  • N/A

Next Steps

  • Complete closure report
  • Complete decommission of ColdFusion FOI system
  • Close project

STU267 CareerHub migration to the Cloud

Category:  Compliance

Milestones

*Planning milestone to be revised and additional milestones to be added*

Milestone Due Date
Completion of project brief 21-Jan-2021
Delivery 27-May-2022
Close 24-Jun-2022

 

RAG Status

AMBER

Report by Susan Ridder-Patrick for February 2022 

 

Achievements this period

  • DPIA was completed and approved by Data Protection Officer
  • Information Security confirmed that penetration testing  of the cloud service would be completed and funded
  • Business areas have been data cleansing in preparation for migration
  • UAT test plans have been completed 
  • Procurement updated that the DPIA concluded the outstanding action for the NCA
  • The development work for the EUCLID data feed has been estimated and scheduled

Issues

  • Industrial action and annual leave has meant the conclusion of the full plan with the supplier has not yet been possible

Next steps

  • Update Data Protocol agreement with SSP
  • Complete project milestones and 3pt estimate to conclude brief
  • Development work to start in April

 

Section Four: Closed or Withdrawn Projects

Only those projects closed from January 2020 onwards are included in this table. A full history of completed projects is available on the programme's website.

Project Info Project Manager's Commentary
STU260 CAM  Degree Finders - Options Appraisal  Project closed in January 2020. The Closure Report is available.
STU266 UG & PG Degree Finder Options Appraisal Project closed in April 2020. The Closure Report is available.

 

 

Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No