Report for August 2013

Report Date
August 2013

Report compiled by Jamie Thin (IS Apps Programme Manager) for Jim McGeorge (SASG), Shelagh Green (Careers), Steve Norman (Careers), John Cavani (C&M) , Ronnie Millar (Counselling) , Sheila Williams (Student Disability Service), Susan Graham (Records Management) (and other business area owners)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

***

 

Section One: Programme Commentary, RAG and Resources Update

 

The Student services programme has 3 projects in progress .

 

Section Two: Projects Not Started

 

 

Project InfoProgramme Manager's Commentary
Various See Annual Plan for 2013-14

 

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary
  

STU233 Open Days and Tours Migration

 

 

Category: Sponsor Funded

Milestones

6-Sep-2013Migration to Test completed
12-Sep-2013Migration to Live completed
26-Sep-2013Deployment Sign Off
04-Oct-2013Close

 

RAG Status

GREEN

 

 Report by Franck Bergeret for Aug 2013

Achievements in last period

  • Brief signed off
  • Migration to Dev completed

Issues

n/a

Next Steps

  • Migration to Test
  • sign off User testing (UAT) and Acceptance stage
  • Migration to Live

 

 

STU234

 

 

Category: Core

Milestones

05-Sep-2013System Analysis sign-off
10-Oct-2013System Build sign-off
25-Oct-2013System Integration & Testing sign-off
29-Oct-2013System Deployment Milestone
01-Nov-2013System Deployment sign-off
08-Nov-2013Project Closure

RAG Status

GREEN

Report by David Watters for August 2013

 

Achievements in Last Period

  • Project start approved by WIS
  • Project brief & plans prepared and submitted to WIS
  • TAD updated for project
  • Development resources assigned to analysis & build stages

 Issues

  • Initial analysis identified potential issue with CCD and possible need for additional effort to address this

Next Steps

  • Sign off system analysis
  • Get estimate for additional CCD work
  • Start on migration of application to CF9

STU235 External Examiners Online Reporting System

 

 

Category: Core

Milestones

n/a

 

RAG Status

GREEN

Report by Franck Bergeret for Aug 2013

 

 

 

Achievements in last period

  • Started initiation and business case

Issues

n/a

Next Steps

  • Sign off business case
  • Complete Brief

 

 

  
  

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary