Report for September 2024
- Report Date
- September 2024
Section One: Programme Commentary, RAG and Resources Update
Commentary
Programme status: The overall status of the STU programme for September 2024 is GREEN.
No RED programme risks this month.
Project Highlights
- STU271: No progress this month
- STU272: The completion rate for Making Transitions Personal Review has surpassed the success of last year with almost 11K returns which is a 56% completion rate
Please note that the project RAG status is following the revised guidelines: A one-page summary of the IS RAG status indicators is available on this page.
Forward Look - September 2024
Resources to end September 2024
Section Two: Projects Not Started
Project | Programme Manager's Commentary |
N/A | All projects are in progress |
Section Three: Projects in Progress
Project Info |
Project Manager's Commentary |
||||||||||||||||||||
STU271 Prospective Student Web Future State Category: Discretionary
RAG Status: GREEN
|
Report by Neil Allison for September 2024Achievements this period
Issues
Next steps
|
||||||||||||||||||||
STU272 Making Transitions Personal Review 24/25 Category: Discretionary Milestones
RAG Status: Green
|
Report by Alexandra Mezeul for September 2024Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Only those projects closed from January 2023 onwards are included in this table. A full history of completed projects is available on the programme's website.
Project Info | Project Manager's Commentary |
STU270 Careers Service Operating Platform | Project closed in July 2023. The Closure Report is available. |
STU268 Making Transitions Personal | Project closed in June 2024. The Closure Report is available. |
STU269 Student Case Management System | Project closed in July 2024. The Closure Report is available. |