Report for April 2018

Report Date
April 2018

Report compiled by  Morna Findlay (IS Apps Programme Manager)

for Jim McGeorge (USG), Niall Bradley (CAM),  Steven Ross (CAM) , Ailsa Vamplew (CAM) , Sheila Williams (SDS), Jane Johnston (SRA),  Damon Querry (RIS), Sara Cranston (Records Management), Rena Gertz (GaSP), Isabell Majewsky Anderson (Edinburgh Global) and other interested business area owners.

***

 

DRAFT

Section One: Programme Commentary, RAG and Resources Update

Commentary

Overall the STU Programme remains AMBER  because there is a risk that not all projects will complete  within 17/18.  The addition of in-year GDPR projects means that planned work is being impacted. Several projects are RED or AMBER at this time.

STU252 - RED - need to agree change of scope and investigate workaround with IS Service Management

STU253 - AMBER - unsuspended and being re-planned  risk that the work cannot be completed in 17/18 hence AMBER.

STU257 - AMBER - planned milestones to be confirmed by project team.

STU263 - RED - planning delayed: not expected to have significant impact on end date of May 19 replacement of FoI tool.

It was hoped that the proposed project to provide free WIFI for Open Days would be superseded by a new JISC service. IS is now participating in the  JISC pilot  soon, but there is a risk that IS may not be able to use this to provide fee WIFI for the June Open Day and that the 10 days earmarked as funding may not be sufficient to supply an alternative service. The programme manager will meet with network services on 16/5/18 to look for a way forward.

RAG & Forward Look April 2018

   

 

 

Resources to end of April 2018

The resources table below below 65d has been nominally allocated to STU263,  (50 d in 17/18) and the budget overall  for 17/18 is is 703d. 

STU257 - the estimate for 17/18 and 18/19 is yet to be confirmed, due to uncertainty over the procurement strategy.

 

  

 

 

Section Two: Projects Not Started

Project Info Programme Manager's Commentary

CAM  Degree Finders - Options Appraisal - PhP End of Life migration path - proof of concept

Planning: Delayed  - was Feb 2018-  now expected to be April 2018

Delivery: July 2018? (TBC after planning) 

RAG Status

RED

Plan

This project to assess the options for replacing the CAM UG & PG Degree Finders given their expected end of life date of November 2020.

The status is RED  as if the application does not work on the new infrastructure then the budget and milestones are likely to be impacted. The start of this  project has been delayed due to resource conflicts within the Project services team  , and is now expected to start during May 2018. New PM has become available - handover from 8th May 

Dependencies

Provision of infrastructure through INF127.

SRA - Free WiFi at University Open Days

Discretionary

Planning: TBC

Delivery:TBC

RAG Status

RED

Plan

 This project is to undertake the work noted in this proposal. The proposal estimated 10d of work, but it is not clear that this would be enough to deliver a standalone solution.

 ITI have expressed the  expectation that JISC will deliver a suitable service in time for the June Open Day, but this is no longer certain, hence the status as RED. This project will not be withdrawn until a clear commitment to provide a solution has been obtained.

Dependencies

Decision on whether the JISC solution is suitable.

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

Milestones

Provisional  milestones updated on Projects website, will need updated after re-plan, once scope change approved

 Date

Title

 

RAG Status

RED

Report by Jamie Thin for April 2018

Achievements in Last Period

  • Some discussion on proposed scope change 
  • No progress with project tasks / JIRAs - resource conflicts on project team

Issues

  • Open - No agreement on Scope change re. Org unit permissions
    • Initial proposal of providing no org unit data restrictions have been rejected by Business lead
    • Workaround to be explored with IS Service Management
  • Open : Resource conflict in IS S/W dev team to deliver outstanding jiras 
  • After scope change agreed, project will need a re-plan

Next Steps 

  • Get change of Scope agreed
  • Deliver Org unit permissions workaround for IGMM and Roslin institute
  • Deliver remaining JIRAS incl STU252-52 (0.5d effort) 
  • Complete testing  including Org unit permissions solution for IGMM and Roslin institute ( 5 d  effort) 
  • UAT acceptance sign-off
  • Handover to BAU  - Confirm policy decision with IS Service Management re. IS L&UC RIS team access to Universe Designer 
    • propose limited access to Universe Designer for RIS team - so RIS can locally make some simple changes  eg.  rename data items and add 'tool-tip' descriptions of each object 
  • Deploy BI Suite Universe to LIVE, switch on daily package to refresh STAR schema in LIVE
  • Deployment review
  • Project Closure

RAG Commentary

RED -Issue - previous proposed solution for cascading Org unit permissions from the Worktribe application permission model to the BI suite universe is not deliverable. Change of scope and workaround being discussed [No SMT action required]

STU253 - PGR Opportunity Finder

Category: Discretionary

Milestones

23-Mar-2018

End of Planning (re-plan following suspension)

RAG Status

AMBER

Report by Geoff Cropley for April 2018

Achievements this period

  • Business analysis work has been updated  and refreshed
  • Mock-up / Prototype built for demonstration to sponsor and Research Information Committee
  • Reconfirmed business requirements with sponsor
  • Project re-plan  completed 5th April 2018
  • Dependencies on other projects removed
  • Project brief refreshed with a view to end of planning on 3rd May
  • Resource requests out with supplier areas

Issues

  • None

Next steps

  • Complete end of planning  to be signed-off through quality assurance process
  • Agree final resourcing for work to complete before end of academic year

STU256 - CAM Degree Finders - Compliance with Legislation & Guidance

Category: Compliance

Milestones

04-May-2018 JIRA 25 Acceptance Testing
09-May-2018 JIRA 25 Deployment
24-May-2018 Closure (JIRAs 1 to 5 and 25)

RAG Status

AMBER

Report by Chris Konczak for April 2018

Achievements in Last Period

  • UAT continuing, a number of JIRAs have been raised and fixed.

Issues

  • Business requested that UAT is extended by two weeks.
  • Project is AMBER on time as deployment and closure dates have been revised and agreed. Resolved.

Next Steps

  • Sign off UAT
  • Deployment to LIVE

STU257 Privacy Impact Assessment Tool

Category: Compliance

Milestones

* The revised projected milestones have still to be confirmed by the project team

27-Apr-2018

Issue Tender

29-Jun-2018

Complete Tender

14-Sep-2018

User Acceptance

28-Sep-2018

Complete User Guides

15-Oct-2018

Deployment to Live

02-Nov-2018

Deployment Sign-Off

02-Nov-2018

Closure

RAG Status

AMBER

  Report by Andy Stewart for April 2018

  Achievements in Last Period 

  • Procurement Question sets
    • Finalised question sets with regards to Functional Requirements, Information Security and Accessibility
    • Reviewed remaining question sets with the project team
    • commenced compiling final set of questions
  • Revised project plan reviewed and approved by project sponsor and project team
  • Early Market Engagement
    • Cost outline for unlimited users supplied by supplier 4
    • reached out through UCISA mailing list to determine approach by other HE establishments, but no response
  • Procurement Activity
    • Prepared Procurement Advert and ITT
    • Prepared Service Risk Assessment
  • Project Budget
    • Clarification of project budget sought via project sponsor

  Issues

  • Additional two weeks required to complete the procurement sets due to constraints on project manager's time. 
  • Final clarification of project budget still to be confirmed with the project sponsor

Next Steps

  • Project to be re-planned to allow additional time to complete procurement question sets
  • Complete initial procurement process with regards to;
    • Complete the Procurement Strategy document
    • Compile procurement question sets with regards to functionality, technical and security
    • Complete and issue tender documentation 

 RAG Commentary

 Issue: Additional two weeks required to complete the procurement sets due to constraints on project manager's time.

STU258 - Careers - Student Alumni Community Networking Platform

Category - Discretionary

Milestones

04-May-2018 Acceptance sign-off
10-May-2018 Push to Live [Vendor]
23-May-2018 Launch of website
15-Jun-2018 Delivery sign-off
29-Jun-2018 Project closure

RAG Status

AMBER

Issue: The current milestones need to be revised in light of the changes to delivery that need to be made after consultation with the vendor.

Report by David Watters for April 2018

Achievements

  • Project team carried out more work on design & marketing
  • Further discussions with vendor on delivery

Issues

  • Milestones to be reviewed

Next steps

  • Complete finalisation of site ahead of final launch
  • Continue implementation planning with business partners

 STU259 FREEDOM OF INFORMATION  GDPR UPDATES

 Category:  COMPLIANCE

 Milestones

   

 Target Datesort descending  Title
 25-May-2018  Project Delivery
 08-Jun-2018  Deployment sign-off Milestone
 15-Jun-2018  End of Project Closure Stage

  

 Rag Status 

 GREEN

  Report by Megan Graham for April 2018

 

Achievements This Period

  • Build on  TEST completion.
  • Test Plan and scenarios completion.

  • Integration milestone completion.

  • UAT completed.

  • Closed RISKS 
  • Deployment to LIVE 26th April 2018 without issues.

Issues

  • None

Next Steps

  • Delivery Milestone approval at WIS.
  • Closure Preparation.

STU262 Electronic Sharing of Responses for GDPR

Category:  COMPLIANCE 

MILESTONES

  Target Datesort descending   Title
 07-May-2018  Build signoff review
 18-May-2018  Integration Complete
 21-May-2018  Acceptance Milestone Completion
 25-May-2018  Delivery sign-off milestone
 11-Jun-2018  Deployment Sign-off - stage complete
 22-Jun-2018  Delivery of Documentation Deliverables
 06-Jul-2018  Closure complete

 

Rag Status:

 GREEN

 

  Report by Megan Graham for April 2018

 

  Achievements This Period

  • Design Solution complete. Build meeting scheduled for w/c  7TH May with RMT.

  • Show and tell performed to RMT to inform configuration and documentation deliverables.
  • Further tests on RMT Test SharePoint site underway.

 Issues

  • None

 

Next Steps

  • Design Solution milestone completion.

  • UAT completion

  • Move to LIVE

 

STU263 - REPLACE INFORMATION REQUEST PLANNING MONITOR TOOL - PROCUREMENT

Milestones

 

End of Planning: 12/4/18

 

Rag Status:

 Amber

Report for April  2018 by Morna Findlay

Achievements this Period

  • Project initiated

 

Issues

Lack of progress due to unavailability of project manager means planning milestone likely to be missed.

 

Next Steps

Complete planning

 

Milestones

End of Planning:  April 12 2017

 

Section Four: Closed or Withdrawn Projects