Report for January

Report Date
January 2021

Commentary

STU Programme is Red as STU265 is Red

STU265 which is delivering the new eCase system for management of the FOI requests. Go Live  delayed as there is a show-stopper with the email configuration which must be resolved before new system can go live. There are also resource conflicts within ISG as some staff are now on furlough , and this has impacted resource availability

 

 

RAG status at end of Jan  2021

 

RAG at 30-Jan 2020

 

 

Actual Spend to end of Jan 2021

 

Actual spend to 30-Jan 2021

 

 

 

 

 

 

 

 

Section Two: Projects Not Started

 

None

 

 

Section Three: Projects in Progress

 

Project Info

Project Managers Commentary

STU265 - G-Cloud replacement of FOI Request planning tool

Category:  Compliance

Milestones

Revised milestones:

Stage

Milestone

Due Date

Plan

Go/No go budget approval

21-May-2019

Analyse

Product Evaluation

26-Jul-2019

Plan

End of Planning

15-Aug-2019

Procure

Purchase and payment of replacement tool prior to the end of the financial year.

07-Aug-2020

Build

Product Implementation

16-Oct-2020

Accept

User Acceptance Testing - Sign Off

18-Dec-2020

Deliver

Go Live

11-Jan-2021

Deliver

Legacy ColdFusion converted to read-only.

11-Jan-2021

Deliver

Migration of Historic Data

08-Feb-2021

Deliver

Deployment Sign Off

16-Feb-2021

Close

Project Closure

05-Mar-2021

Deliver

Legacy ColdFusion Decommissioned

26-Mar-2021

Rag Status: RED

Report by Alan Donald for Jan 2021

 

Achievements

  • OSIC Report delivered and testing underway
  • Training underway for essential users

Issues

  • Email integration not resolved - use of Authenticated Mail Relay not possible by Fivium - use of Sender Policy Framework now being followed up 
  • OSIC Reports not due to be delivered until early January
  • Delivery and Closure milestones pushed back further due to UAT 

Next Steps

  • Records Management complete UAT of OSIC report
  • RMS complete customisation of eCase
  • RMS carry out training of essential users
  • Launch eCase
  • Agree SLA/OLA with Production Management

 

 

CLOSED Projects

 

 

 

STU252 - Worktribe BI Suite Universe - Research Management BI MI Enhancements

Category: Discretionary

RAG Status

BLUE (Closed) 

Report by Jamie Thin 

STU253 - PGR Opportunity Finder

Category: Discretionary

RAG Status

BLUE (Closed)

Report by Geoff Cropley 

 

 

STU257 Privacy Impact Assessment Tool

BLUE (Closed)

Report by Andy Stewart

  • Project closed Dec 2019
  • Closure report

STU258 - Careers - Student Alumni Community Networking Platform

Category : Discretionary

RAG Status

BLUE (Closed)

Report by Richard Bailey 

 

STU260 CAM  Degree Finders - Options Appraisal 

Category:  Compliance

RAG Status:

BLUE (Closed)

Report by Chris Konczak 

STU263 - Options Appraisal for Replacement of INFORMATION REQUEST PLANNING MONITORING TOOL 

Category:  Compliance

BLUE (Closed)

Report by Ken Miller

STU264 - CAM UG & PG Degree Finders Small Enhancements

Category: Discretionary

RAG Status

BLUE (Closed)

 

Report by Chris Konczak

STU266 - UG & PG Degree Finder Options Appraisal

Category:  Discretionary

Rag Status: 

BLUE (Closed)

Report by Kevin Hone 

 

  • Project closed April 2020
  • Closure Report

 

AttachmentSize
Image icon RAG at 30-Jan 202126.08 KB
Image icon Actual spend to 30-Jan 202120.35 KB
Programme Status
RAG Status
Overall
RED
Has formal escalation taken place?
No
RAG Commentary
RED Issue - Show-stopper with email config for eCase , requires sub-domain to be created, call open with ITI CIS team, no action required by Senior leadership team , ITI CIS team are aware of urgency of the call