May 2015

Report Date
May 2015

 

 

Report compiled by Maurice Franceschi, (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: GREEN

The programme has a large number of ('Apps') projects reflecting the activity and expectations being generated in the TEL area. Amongst its challenges and opportunites, there is the new LTW division and changes in the way of working and relationships with rest of IS which that will bring. So an exciting time.

Several projects have moved to Amber this month, as they replan to around resource conlficts and technical issues that have arisen.

However, the expectation is that all projects are moving back to Green within the next week or two.

In terms of budget, there is a challange with some days needed to be found for projects carrying over unplanned into 2015/16.

For this year. after some expected final transfers of contingency to projects in June, we expect to have a substantial effort of around 50 days to retuern to the ISG portfolio, and also to do an early start for Moodle Data Feeds.

 

IS Applications Projects

 

 

USD Projects

Planning not in place.

 

IS Applications Budget

 

Section Two: Projects Not Started

 

Project InfoProject Manager's Commentary
Working with APPS 
 all project which were planned now started/completed. We will assess the potential for an in-year moddle data feeds project, in June.
LTW Projects 
VLE STudent Analytics - MoodleTEL019
ePortfolio Gap Analysis 
TAG Assessment Tools 
TREETEL020
Also note there are two other projects of interest to TELMultimedia Procurement and Multilemedia Implementation - Major Projects being delivered by the separate Multimedia Programme, but which will be services supported by TEL once delivered.
  

 

 

 

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

TEL011 (AP34-049)

Next Generation Personal Response System (PRS) - Procurement

Compliance  

 

Milestones   

 
29-May-2015Sign Contract
12-Jun-2015Closure

 

RAG Status

GREEN

 

Report by Maurice Franceschi for May 2015

There have been a series of teleconferences to discuss and resolve a number of contract points.

The end is in sight, and we hope that a teleconference on 2nd June will be out last, and that then the contract can be completed. The length of this negotiation has meant the budget has been exceeded by a couple of days.

 

Achievements in Last Period

  • write up T&C's and agree contract - not completed
  • write an SLA - not completed

Issues

  • no issues at this stage
  • no amber or red risks

Next Steps

  • write up T&C's and agree contract
  • write an SLA

 

 

 

 

 

 

 

TEL013

Learn Automated Failover

Milestones

None

 

RAG Status

BLUE

Report by Colin Forrest for May 2015

Achievements in the Last Period

  • The  work has been completed and the project is now closed

 

TEL015 (AP45-039)

Online Assessment/Feedback Evaluations – FACS

Milestones:

 

01-Oct-2015End of suspension

 

RAG Status

 

SUSPENDED

 

Report by Sue Woodger for April 2015

 

TEL015 suspended for 6 months until 1 October 2015.

 

Next Steps

End of Suspension 1 Oct 15

 

TEL017 (AP45-038)

VLE Student Analytics

Milestones

New 
6-Jul-2015Build stage 2
30-Jul-2015Accept stage 2
03-Aug-2015Delivery
18-Aug-2015Deployment sign-off review
31-Aug-2015Closure

RAG Status

GREEN

Report by Morna Findlay for May2015

Achievements this period

  • Build stage begun
  • Build of exctract completed
  • Performance criteria under discussion

Issues

  • No known issues

Next Steps

  • Build of building block to commence
  • Build stage to complete

 

 

TEL018 (AP45-037)

QMP Upgrade

Milestones:

 

15-Jun-2015 Integrate (QMP Consultancy)Integrate   
17-Jul-2015 End of UATAccept   
20-Jul-2015 Acceptance Sign Off (ASOR)Accept   
28-Jul-2015 DeploymentDeliver   
06-Aug-2015 Deployment Sign Off (DSOR)Deliver   
20-Aug-2015 ClosureClose   

 

RAG Status

AMBER

Report by Colin Forrest for May 2015

Achievements in the last period

  • Our consultancy date with QMP has been agreed and it will occur on the 15th of June.
  • The statement of work has been signed by QMP and LTW.  It includes updating TEST to v5.7 and signing off an implementation plan for our LIVE deployment.
  • Our project resources have been rebooked to match the new timetable.
  • We have prioritised and replanned the tasks to be performed once the upgrade of TEST has been completed.

Issues

  • The schedule is for a deployment before the end of July.  This is a tight timescale however we have resources in place to perform our tasks.
  • It should be noted that we have made several attempts internally to upgrade our QMP version so there is a risk that the one day of consultancy will not be sufficient to perform the upgrade.  We may have further contingency monies available to us for additional consultancy should it be required. 

Next steps

  • Successfully upgrade TEST.
  • Perform the Config, Load Tests and Resilience tests in TEST.
  • Sign off the UAT and proceed with our implementation plan for LIVE.

TEL021 (AP45-039)

TELS Management Information

Discretionary  

 

Milestones   

05-Jun-2015End of BuildBuild
12-Jun-2015Acceptance Sign-OffAccept
24-Jun-2015DeliveryDeliver
08-Jul-2015Deployment Sign-OffDeliver
15-Jul-2015ClosureClose

 

 

 

RAG Status

GREEN

Report by David Watters for May 2015

 

 

Achievements in Last Period

  • Build stage completed
  • User testing started in DEV

Issues

  • Build stage not fully signed off
  •  Original design for feed from MySQL had to be replanned

Next Steps

  • Sign-off build stage
  • Complete user testing and acceptance sign-off

TEL022 (AP45-058)

Moodle Upgrade

Compliance  

 

Milestones   

 

12-Jun-2015Build ReviewBuild
24-Jul-2015Acceptance Sign OffAccept
07-Aug-2015DeliveryDeliver
14-Aug-2015DSOR (Delivery Sign Off)Deliver
28-Aug-2015ClosureClose

 

 

 

RAG Status

AMBER

Report by Colin Watt for May 2015

Achievements in Last Period

  • New infrastructure delivered by ITI and DEV platform built alongside existing service (however, technical issues prevented this from being completed to achieve delivery in the preferred window, see issues below).
  • Agreement with ITI that they will now support RHEL 7.1 (not an option when Design and TAD agreed and signed off)
  • ITI requested to rebuild infrastructure using RHEL 7.1
  • Agreement on approach for revised plan with Project Sponsor and Business Lead: complete build on RHEL 7.1 platform and review at that point; revised scheduled proposed which includes 4 weeks of UAT, but will now push delivery into August.

 

Issues

  • Puppet configuration tools were used to build a deployment platform for the DEV Moodle environment. However, despite the versions of the software components appearing to be compatible, issues in the dependency tree made it impossible to deliver  a platform without manually compiling components, which is unsustainable for support. This issue is not related to the Puppet automation tools delievered by INF108, but to the components available in RHEL 6 and software collections. The immediate recommendation from the Senior Supplier was to have the infrastructure rebuilt using RHEL 7.1, which ITI have now agreed to support (this was not an option when the TAD was signed off). The rebuilt infrastructure was expected to be handed over by 27/05/15 but was delayed until end of the business day 29/05/15.
  • Project Sponsor has requested with Programme Manager that the project be raised to a priority 1.
  • Business acknowledge that the revised timeline could be derailed by technical issues on RHEL 7.1 as described in Risk 6, as this is the first service DevTech will be deploying a service to. 
  • Risk logged regarding potential dependencies in RHEL 7.1 / Moodle 2.8 which could derail the project - for this reason the RAG status is Amber on Time and Cost, and Amber overall, until successful build review.

 

Next Steps

  • Complete build of new platform on RHEL 7.1.
  • Review of milestones and timeline based on build review.
  • PM to work with Business Lead on updates to EqIA.

 

TEL023 (AP34-049)

Next Generation Voting System Implementation

Compliance  

 

Milestones   

 
15-May-2015End of Build - Dev Environment with Integration with SSO
28-May-2015End of Build - Dev Environment with Integration with Learn
29-May-2015Communications Plan (for Launch) in Place
19-Jun-2015User Acceptance Sign-Off and Load Testing Sign-Off
01-Jul-2015Delivery to Live - Launch of Top Hat
13-Jul-2015Deployment Sign-Off - handover to LTW and Apps Production Support
22-Jul-2015Project Closure

 

RAG Status

AMBER

Report by Maurice Franceschi for May 2015

 

There have been technical issues both for the Learn and for the SSO integrations, and the Silent Install is not tested completely. Nothing major, but the SSO is now two weeks late, and Learn is also missed.

A team meeting on 5th June will review progress expected for w/c 1st June, and also feedback from UAT, and then assess and potentially re-define the milestones.

Project moving to Amber status.

Achievements in Last Period

  • Check the fixes/ehancements identified as priority - done
  • Start UAT - done
  • Initial testing of Shibboleth Integration - not done
  • Initial testing of Learn Integration - not done

Issues

  • the two integration and the silent install are issues being monitored
  • no amber or red risks

Next Steps

  • complete UAT
  • complete testing of Shibboleth Integration
  • complete testing of Learn Integration
  • complete testing of SIlent Install

 

TEL024

TEL024 Migration of MVM UG to PebblePad

Discretionary

Milestones

 

01-Jun-2015Access project complete
01-Jun-2015Training materials and documentation
05-Jun-2015Year 4 ready for submissions
19-Jun-2015Year 5 ready for submissions
27-Jul-20152015/16 Plan
14-Aug-2015Year 3 ready for submissions
11-Sep-2015Year 2 ready for submissions
11-Sep-2015Year 1 ready for submissions
25-Sep-2015Closure

 

 

RAG Status

GREEN

 

Report by Sue Woodger for May 2015

 

Achievements

  • Year 5 mapping is complete with PebblePad set up complete
  • Year 4 mapping complete - PebblePad set up complete (just some formatting to do)
  • Confirmed that no items can be added to the existing MBChB Portfolio in EEMeC as from the start of each academic year
  • Additional MVM portfolio items have been confirmed
  • Communications plan signed off 15 May
  • Access project complete and signed off on 3 June
  • EEMeC page set up to disseminate information about the changes to PebblePad for staff and students
  • Non UoE addresses in VRS resolved with workaround with the help of Graeme Wood - Dave Berry Section Head of Development Services has asked us to feed VRS issues to him to feed into the Technical Peer Group.
  • Drop-in training session for Year 4 markers held on 29 May
  • Closed risk 2 - system performs poorly - we are happy that Pebble can support the submissions for all years.They confirmed with LTW that Pebble Learning can support 10,000 submissions per year and that ATLAS has no number limits for submissions.
  • Closed risk 4  - Availability of IS Skills - IS Skills are engaged to take on staff training for PebblePad
  • Closed risk 6 - Unable to recruit temp staff member results in project delays - a temporary member of staff, Kate Findlay, has been appointed to support Lydia - offering data support for the PebblePad project
  • Closed risk 7- the feed between IDM and PebblePad has been fixed - previously to get students and staff into PebblePad the process had to be done manually which created longer timescales and required additional resource

 

Issues

  • There is an issue where NHS markers are unable to access our system through the firewalls on NHS premises meaning they cannot access PebblePad to download the marking. Have tested NHS Lothian sites and access is available. There will now be further testing involving non NHS Lothian sites (such as Dumfries)

 

Next Steps

  • Lydia Crow scheduling further meetings for markers that could not make the session on 29 May
  • Year 4 and 5 set up: Workspaces populated with assignments for Years 4 and 5 will be completed and access tested by markers
  • Years 1-3 set up to be completed
  • Identified markers and module leads will test their access to PebblePad by 5 June
  • Training materials complete by 5 June
  • Training meetings for Year 4 co-ordinators scheduled for 8 June
  • Training meetings for Year 5 co-ordinators scheduled for 24 June
  • Lydia Crow meeting with Jenni Houston of IS Skills to finalise training plan 25 Jun

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

TEL014 (AP45-059)

Online Assessment/Feedback Evaluations - Adaptive Learning

Project closed 27 April 15