September 2015
- Report Date
- September 2015
TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Mark Wetton and Anne-Marie Scott
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Overall Programme RAG: GREEN
TEL017 VLE Student Analytics - Closed.
TEL018 QMP Upgrade - Closed.
TEL021 TELS Management Information - Moodle deployment taking place w/c 05/10. DSOR and closure to follow.
TEL022 Moodle Upgrade - Closed.
TEL023 Next Generation Personal Response System Implementation - Closed.
TEL024 Migration of MVM UG to PebblePad - Closed.
TEL025 Moodle Data Feeds - Planning complete; scope and cost is subject to review by Architecture group of the proposal.
Forward Look and RAG
Resource Summary
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
AP56-010 BlackBoard Collaborate MyEd Channel Refresh | Scheduled start: August 2015; delayed: awaiting further detail from Blackboard which will determine likely start date. |
AP56-012 Coldfusion Upgrade of Learn Services MyEd Channel | Scheduled start: January 2016; it is understood that this project is now not required (tbc) |
AP56-013 Annual Moodle Upgrade | Scheduled start: January 2016 |
AP56-079 VLE Student Analytics | Scheduled start: January 2016 |
AP56-080 Online Assessment Evaluations (years 2 and 3) | Scheduled start: tbd |
AP56-035 Learn and Student Record Grade Exchange | Scheduled start: October 2015; delayed: PRICCL required to transfer 10 days effort from the TEL programme to the SSP Programme to cover R&D under their existing project. |
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||||
Online Assessment/Feedback Evaluations – FACS Milestones:
RAG Status
SUSPENDED
| Report by Sue Woodger for April 2015TEL015 suspended for 6 months until 1 October 2015.
Next StepsEnd of Suspension 1 Oct 15
| ||||||||||||||||||
TELS Management InformationDiscretionary
Milestones
RAG Status AMBER | Report by David Watters for September 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
TEL025 TEL025 Moodle Data Feeds Discretionary Milestones
RAG Status GREEN | Report by Karen Stirling for September 2015 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
VLE Student Analytics | Closure Approved 04 September 2015 |
QMP Upgrade | Closure Approved 25 September 2015 |
Moodle Upgrade | Closure Approved 11 September 2015 |
Next Generation Voting System Implementation | Closure Approved 11 September 2015 |
TEL024 Migration of MVM UG to PebblePad | Closure Approved 02 October 2015 |