December 2015

Report Date
December 2015

TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Anne-Marie Scott

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Overall Programme RAG: GREEN

 

TEL021 TELS Management Information - closure approved.

TEL025 Moodle Course Enrolment Management - Design review signed off.

Programme Manager and ISG Portfolio Manager have reconciled budget. Programme Balance row now 68 Days.

AP56-012 Coldfusion Upgrade of Learn Services MyEd Channel to be withdrawn, and 20 Days to be transferred to WIT Programme to contribute towards testing of MyEd channel (WEB008).

AP56-013 Annual Moodle Upgrade to be started in December 2015. Scope potentially extended to include resilience.

 

Forward Look and RAG

 

 

 

Resource Summary

 

Section Two: Projects Not Started

 

Project InfoProject Manager's Commentary
AP56-010 BlackBoard Collaborate MyEd Channel Refresh

Scheduled start: August 2015; delayed: likely start date Jan 2016 based on latest information on APIs from Blackboard.

AP56-012 Coldfusion Upgrade of Learn Services MyEd ChannelScheduled start: January 2016; project is now not required (due to work done on MyEd channel enhancements in WEB008)
AP56-013 Annual Moodle Upgrade

Scheduled start: January 2016

AP56-079 VLE Student AnalyticsScheduled start: January 2016
AP56-080 Online Assessment Evaluations (years 2 and 3)Scheduled start: November 2015; TEL029 Adaptive Learning Pilot started using 20d from umbrella project.
AP56-035 Learn and Student Record Grade ExchangeScheduled start: October 2015; delayed: likely start Jan 2016 dependent on R&D by SSP.

 

 

Section Three: Projects in Progress

 

Project InfoProject Manager's Commentary

TEL025

TEL025 Moodle Course Enrolment Management

Discretionary

Milestones

 

11-Dec-2015Build Complete
18-Dec-2015Integration Complete
12-Feb-2016Acceptance complete
18-Feb-2016Deployment complete
25-Feb-2016Deployment Review complete
04-Mar-2016Closure

RAG Status

GREEN

Report by Karen Stirling for December 2015

Achievements in Last Period

Issues

Next Steps

 

The project status is GREEN

TEL029

Adaptive Learning Pilot

Discretionary

 

Milestones

11-Dec-2015Planning
13-Jan-2016Analytics Configuration Semester 2
13-Jan-2016Update current coursework materials
15-Jan-2016Deploy current coursework materials updates
18-Jan-2016Development of new materials
18-Jan-2016Deploy Analytics Semester 2
22-Jan-2016Deploy new materials
15-Feb-2016Analytics Configuration Semester 1
19-Feb-2016Feedback Survey results updates
22-Feb-2016Deploy Analytics Semester 1
31-Mar-2016Feedback Survey results new materials
11-Apr-2016Deployment review
18-Apr-2016Close

 

 

RAG Status

GREEN

 

Report by Sue Woodger for December 2015

Achievements in Last Period

 

Issues

 

Next Steps

 

TEL030

Annual Moodle Upgrade

Compliance

 

Milestones

 

 

RAG Status

GREEN

Report by Colin Forrest for December 2015

Achievements in Last Period

Issues

Next Steps

 

The project status is GREEN

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

TEL017 (AP45-038)

VLE Student Analytics

Closure Approved 04 September 2015

TEL018 (AP45-037)

QMP Upgrade

Closure Approved 25 September 2015

TEL022 (AP45-058)

Moodle Upgrade

Closure Approved 11 September 2015

TEL023 (AP34-049)

Next Generation Voting System Implementation

Closure Approved 11 September 2015

TEL024

TEL024 Migration of MVM UG to PebblePad

Closure Approved 02 October 2015

TEL021 (AP45-039)

TELS Management Information

Closure Approved 04 December 2015

TEL015 (AP45-039)

Online Assessment/Feedback Evaluations – FACS

Withdrawal Approved 24 November 2015