August 2020

Report Date
August 2020

(Draft) TEL Programme Report compiled by Colin Watt, (IS Apps Programme Manager) for Programme Owner Karen Howie

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

 

Section One: Programme Commentary, RAG and Resources Update

 

Projects in Progress:

 

TEL057 Learn Foundations

TEL063 Lynda.com upgrade to Linkedin Learning

TEL068 EExams Procurement

 

 

Forward Look and RAG

Resource Summary

Section Two: Projects Not Started

None

 

 

Section Three: Projects in Progress

 

Project Info Project Manager's Commentary

TEL057

Learn Foundations

Discretionary

Milestones:

Milestone

Due Date

Complete

Phase Two: Report on measurement against success (D9.03)

30-Nov-2020

No

Phase Two: Evidence on Phase One completed - Report Produced (D9.04)

30-Nov-2020

No

Phase One: Evaluation Framework Sign Off

30-Nov-2020

No

Phase Two: Evaluation Baseline Completed (D9.01)

30-Nov-2020

No

Project Closure

29-Jan-2021

No

RAG Status: GREEN

Report by Lee-Ann Simpson for Aug 2020

Achievements in the last period

  • Focus for August: School migration on Learn
  • The Learn Foundations project is currently working with 20 Schools/Deaneries to support in Semester 1 preparations:
    • 13 School migrations completed by the core intern group
    • 3 School migrations completed locally
    • 2 School migrations in progress
  • Additional conversations undertaken with all Schools resulting in additional support being offered/accepted by Schools in their preparations for Semester 1.
  • 20 x students extended for 1 month from the 21st August to support in the additional support being offered and accepted by Schools.

 

Issues

  • None to report

Next Steps

  • Continue on the migration workstream and supporting preparations for teaching in Semester 1:

    • Additional support conversations with partner Schools in preparation for Semester 1 to be continued.

TEL063

Lynda.com upgrade to Linkedin Learning

Compliance

Milestones:

RAG Status:

BLUE (suspended)

Report by Kevin Hone for Aug 2020

TEL068

EExams Procurement

Compliance

Milestones:

End of Planning 11th September.

RAG Status: 

Green.

Report by Colin Forrest for Aug 2020

Report Date
August 2020

Last Month

  • The Project Board was setup.
  • We had numerous User Discussion Sessions with participants from 10 schools.
  • The Project Brief has been drafted.
  • We explored the best way to proceed with the procurement.  2 lots.  One for the central replacement and the second for the particular requirements of CMVM.

Issues

  • None.

Next Steps

  • The 1st board.
  • Sign off Planning.
  • Build the requirements.

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

TEL064

Moodle Upgrade

Closure Approved 14/08/20

 

Has formal escalation taken place?

No
AttachmentSize
Image icon tel-flook-aug20.jpg158.17 KB
Image icon tel-effort-aug20.jpg142 KB
Programme Status
Has formal escalation taken place?
No