Our future year funding has been removed, however this year's does stay in place.
Work completed
The team have drawn up a list of improvements that can realistically be taken forward during Covid.
Each of these improvements come from the evidence collected during our student survey work.
This list is being priced and will be taken tot he Steering Group.
TSG005
Remote Support for Teaching Spaces
Discretionary
RAG Status
Green
Report Date
May 2020
Next Steps
Development continues.
Issues
Getting access to the required Timetabling data may require a further project next year.
There is no funding in place for next year. We are working with the timetabling support team to gain a snapshot of the timetabling data that can be used to facilitate this year's development.
Work completed
Design and development time has been agreed with EDINA.
The design review has taken place and development is due to begin.
TSG004
Specialist Teaching Spaces
Discretionary
RAG Status
Red
Report Date
May 2020
Next Steps
Make the purchases of equipment.
Issues
Our future year funding has been removed, however this year's does stay in place.
Storage and installation, but as mentioned these points are being worked through.
Work completed
Purchase orders are ready and the team are working through the logistics of storage and installation costs (which would fall into next year).
The Learning Spaces team management have been in close contact with colleges to ensure we are adapting plans and purchasing kit that can be used during the current Covid situation.
TSG006
AV Loan Services
Discretionary
RAG Status
Green
Report Date
May 2020
Work completed
Interviews/focus groups completed
Demo of SISO system for stakeholders
Analysis of qualitative data
First results from analysis shared with Project Team and Steering Group