July 2020

Report Date
July 2020
Report Date
July 2020

Overview:

The Teaching Spaces Oversight Group (TSOG) approved the plans for this programme during January 2020..

 

Overall Programme RAG:

Green

 

Projects in Progress:

Code   RAG Manager Status Stage
TSG003 Teaching Space Student Helpers Green Colin Forrest Suspended Execute
TSG004 Specialist Teaching Spaces Green Colin Forrest Suspended Execute
TSG005 Remote Support for Teaching Spaces Green Colin Forrest Suspended Execute
TSG006 AV Loan Services Review Green Karen Beggs Closed Execute

 

Project Reports

TSG003 

  

Report Date
July 2020

Last Month

  • The project has been put on pause due to 20/21 funding being pulled.
  • The Teaching Space Oversight Group will keep this work within their future agenda and will restart the work once we have students back on campus.  

Issues

  • No further issues.

Next Steps

  • The project has been paused.

TSG005

Remote Support for Teaching Spaces

 

Discretionary

 

RAG Status 

Green

Report Date
July 2020

Last Month

  • The project has been put on pause due to 20/21 funding being pulled.
  • The Teaching Space Oversight Group will keep this work within their future agenda and will restart the work once we have students back on campus.  

Issues

  • No further issues.

Next Steps

  • The project has been paused.

TSG004

Specialist Teaching Spaces

 

Discretionary

 

RAG Status 

Red

Report Date
July 2020

Last Month

  • The project has been put on pause due to 20/21 funding being pulled.
  • The Teaching Space Oversight Group will keep this work within their future agenda and will restart the work once we have students back on campus.  

Issues

  • No further issues.

Next Steps

  • The project has been paused.

TSG006

AV Loan Services

Discretionary

 

RAG Status 

Green

Report Date
June 2020

 

 

Work completed

  • First draft of paper shared with Project Team and Steering Group
  • Options discussed with Steering Group and narrowed down

Issues

  • None

Next steps

  • Short-term sub-group to define new web page
  • Discussions with Library senior management re longer term plans
  • Final paper to be agreed
Programme Status
RAG Status
Overall
BLUE
Has formal escalation taken place?
No
RAG Commentary
Funding for 2020/2021 was pulled due to the pandemic. The programme may reopen at a later date.