Report for August 2024

Report Date
August 2024

USD Monthly report for Neil Bruce (Programme Owner) for August 2024.

Section One: Commentary, RAG, and Resources Update

Programme Commentary

August monthly report for USD Programme. 

RAG Status and Forward Look

Resources

 

Section Two: Projects to be Started

Project Info Commentary
Move IS Alerts System to the Cloud start date tbc
UniDesk Archive start date tbc

Section Three: Projects in Progress

Project Info

Project Managers Commentary

ISG027 ISG Website Migration 

Milestones

Change Freeze Starts 30-Sep-2024
Migration Review 04-Nov-2024
Migration Complete - ISG Website Live on EdWeb 2 (Major) 11-Nov-2024
Closure Review (Major) 29-Nov-2024

RAG:

GREEN

Report by Anna Forostianko for August 2024

Achievements this period

  • TEST migration complete
  • EdWeb2 Training for Lead Publishers underway
  • Lead Publishers on track with the migration preparation

Issues

  • The dates for the start of Change Freeze and Migration Completion have changed (30 Sep & 11 Nov respectively) due to the complexity of the ISG Website and resourcing within the Migration Team. The new milestone dates below, Apps Review log underway. See change log
  • Some section editors have limited capacity for the migration preparation & EdWeb2 training. They have been communicated the risks, and their pages might migrate as is.See issue

Next Steps

  • Start LIVE migration

 

 

USD028 Card Implementation

Milestones

RAG

AMBER

Report by Colin Watt for August 2024

This is a restricted project. Those with access will be able to view the August report on the project's website.

Link to secure report

USD029 Printer Fleet Contract

Milestones

RAG

RED

Report by Colin Watt for August 2024

This is a restricted project. Those with access will be able to view the August report on the project's website.

Link to secure report

USD031 Business Continuity for ISG Services

Milestones

 

Completed BIAs for Phase 2 assets 31-May-2024
Build secondary technical option for BCP Storage Solution 07-Jun-2024
Deliver BCP Storage Solution - Primary and Secondary 28-Jun-2024
Completed BCPs for all Directorates and Phase 2 assets 31-Jul-2024
Project Closure 30-Aug-2024

RAG

RED

 

Report by Sonali Nakhate for August 2024

Achievements this period

  • BCP primary storage solution final build completed, though integration with the secondary data store is pending.
  • Secondary solution storage costs – costs received and procurement is complete.
  • Project will then be closed.

Issues

  • Delay in securing costs for secondary solution has meant that the BCP storage solution delivery could not be completed. Subsequent discussions with DevTech and SharePoint team has led to a possibility that setup of Google Cloud might take longer than originally anticipated.
  • Delay in receiving credentials from Computacentre for the procured Google Cloud platform.

Next Steps

  • Receive credentials from Computacentre for the procured Google Cloud platform.
  • BCP Secondary solution to be setup and integrated, with Devtech's help.

USD032 ISG Staff Intranet

Milestones

 

Complete Prototype testing 15-Aug-2024
End of Design 23-Aug-2024
Phase 1 Content created 01-Oct-2024
Complete Build of Staff Intranet 18-Oct-2024
Complete UAT 01-Nov-2024
UAT Acceptance Review 08-Nov-2024
Deliver - Test complete, ready for go-live - Major 11-Nov-2024
Closure - Major 13-Dec-2024

RAG

AMBER

 

Report by Sonali Nakhate for August 2024

Achievements this period

  • UX testing completed with outcomes from the testing shared with the User Group and Project Board and JIRA stories amended accordingly.
  • Design phase continues with SharePoint Architect working on creation of Design and Architecture documents. There has been a couple of weeks' delay but it is anticipated that this should not impact the final build dates
  • Permissions Model - work ongoing with content owners to identify the SharePoint roles: Content Owners, Writers, Editors and Readers, which will inform the structure of the ISG Staff Intranet

Issues

  • User engagement is patchy due to staff sickness and holidays and has delayed finalisation of the user stories and permissions model.
  • Sign off and finalisation of some user stories has been impacted due to staff availability issue -  Availability of Facilities colleagues | Project Management (ed.ac.uk)
  • Design stage has been delayed by a couple of weeks' due to SharePoint resource's availability due to leave and other higher priority work.

Next Steps

  • Awaiting direction from SLT on how we should be proceeding with the project.
  • Complete Design of the new Intranet, in readiness for build to commence.
  • Sign off of the Information Architecture by the Project Board

USD033 Cloud Printing Implementation Phase 

Milestones

RAG

BLUE (suspended)

Report by Colin Watt for August 2024

Project currently suspended

USD034 IT & Library Business Service Readiness for Start of Semester 24/25

Milestones

IT & Library Readiness Weekly Reporting Ends 06-Sep-2024
International Arrival and Start of Welcome Week (External Milestone) (D2.1) 07-Sep-2024
Start of Teaching Week 1 (External Milestone) 18-Sep-2024
Start of Teaching Week 2 (External Milestone) 25-Sep-2024
Delivery Sign Off Review following Start of Session - Major 17-Oct-2024
Project Closure - Major 02-Dec-2024

RAG

AMBER

Report by Tim Gray/Anna Forostianko for August 2024

Achievements this period

  • Welcome Week Planning Milestone achieved.
  • Social Media content is almost completed
  • All purchases have been completed and the majority delivered
  • Piper for 7th and 8th September 2024 secured and PO raised
  • IT Readiness meetings well attended
  • The date for the Principal's visit to ML confirmed
  • PM has reported progress to SLT

Issues

  • Facilities are stating that they are short-staffed and there is a risk that they do not have adequate staff to facilitate a smooth running of Welcome Week. 
  • The room booked for the project team during welcome week has been pulled due to renovation work. An secure alternative room needs to be found.   

Next Steps

  • Complete all planning
  • Hand over IT Readiness Strand to daily meetings during WW and week 1
  • Hold Welcome Week
RAG Commentary
Issue: Facilities are two team members down due to illness and the recruitment freeze.
Impact: Facilities run the queue management and floor plan for Welcome Week. There is a risk that the smooth management of these areas is impacted by the staffing issues in Facilities. If there are not adequate staff on the ground, this can result in a negative impact on students in the Main Library.
Next steps: The project team will meet with Facilities before Welcome Week to discuss possible solutions and assist during Welcome Week where possible.

Section Four: Closed or Withdrawn Projects 2023/24

Project Info.    Project Managers Commentary

 

 

 

Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No
RAG Commentary
Overall Programme RAG status this month is AMBER.