Report for October 2024

Report Date
October 2024

(draft) USD Monthly report for Neil Bruce (Programme Owner) for October 2024.

Section One: Commentary, RAG, and Resources Update

Programme Commentary

October monthly report for USD Programme. 

RAG Status and Forward Look

Resources

 

Section Two: Projects to be Started

Project Info Commentary
Move IS Alerts System to the Cloud project to be started 04/11/24.
UniDesk Archive start date tbc - to be reviewed with USD again in December.

Section Three: Projects in Progress

Project Info

Project Managers Commentary

ISG027 ISG Website Migration 

Milestones

Migration Complete - ISG Website Live on EdWeb 2 (Major) 11-Nov-2024
Closure Review (Major) 29-Nov-2024

RAG:

GREEN

Report by Anna Forostianko for October 2024

Achievements this period

  • ISG Website Migration complete
  • Site handed over to Lead Publishers for review

Issues

  • Some section editors have limited capacity for the migration preparation & EdWeb2 training. They have been communicated the risks, and their pages might migrate as is. See issue  

Next Steps

  • Sign off the migrated ISG site
  • Close the project

USD028 Card Implementation

Milestones

RAG

AMBER

Report by Colin Watt for October 2024

This is a restricted project. Those with access will be able to view the October report on the project's website.

Link to secure report

USD029 Printer Fleet Contract

Milestones

RAG

GREEN

Report by Colin Watt for October 2024

This is a restricted project. Those with access will be able to view the October report on the project's website.

Link to secure report

USD031 Business Continuity for ISG Services

Milestones

Build secondary technical option for BCP Storage Solution 18-Oct-2024
Major - Deliver BCP Storage Solution - Primary and Secondary 18-Oct-2024
Project Closure 31-Oct-2024

RAG

GREEN

Report by Sonali Nakhate for October 2024

Achievements this period

  • Secondary solution storage – domain purchase and setup complete.
  • Work ongoing on updating the user manual for the BCP Repository solution following feedback from USD team.

Issues

None

Next Steps

  • Complete User Manual and handover system to USD
  • Send comms to Service Managers/Service Owners about the solution and populate it with services and documents for the 12 services in scope of the project.
  • Additional work for  University wide BCP solution is under consideration (awaiting decision on funding) and hence might affect project scope and project closure.

USD032 ISG Staff Intranet

Milestones

Complete Prototype testing 15-Aug-2024
End of Design 23-Aug-2024
Phase 1 Content created 01-Oct-2024
Complete Build of Staff Intranet 18-Oct-2024
Complete UAT 01-Nov-2024
UAT Acceptance Review 08-Nov-2024
Deliver - Test complete, ready for go-live - Major 11-Nov-2024
Closure - Major 13-Dec-2024

 

RAG

AMBER

 

Report by Sonali Nakhate for October 2024

Achievements this period

  • Design phase continued with SharePoint Architect working on creation of Architecture document while simultaneously starting on the preliminary build. There has been some delay in this phase due to limited SharePoint architect time.
  • Project Board meeting was held this month and was attended by Gavin McLachlan and Stefan Kaempf to discuss the issues related to RED RAG status. Overall agreement to progress with the project and funding and resourcing to be discussed with Stefan separately.
  • Project Board signed off the proposed Information Architecture of the site.
  • Reviewed outstanding work and estimates.

Issues

Next Steps

  • Secure funding and required resources on the project.
  • Continue with Build and documenting SharePoint Architecture of the new site.

USD033 Cloud Printing Implementation Phase 

Milestones

RAG

BLUE (suspended)

Report by Colin Watt for October 2024

Project currently suspended

USD034 IT & Library Business Service Readiness for Start of Semester 24/25

Milestones

Delivery Sign Off Review following Start of Session - Major 17-Oct-2024
Project Closure - Major 02-Dec-2024

RAG

AMBER

Report by Tim Gray/Anna Forostianko for October 2024

Achievements this period

  • Informal project reviews completed for different areas

Issues

  • Delivery Sign Off review delayed until one of the PMs is back from sick leave. Change request underway

Next Steps

  • Complete formal project review
  • Close the project

USD036 Move IS Alerts System to the cloud

Milestones

To be agreed in planning.

RAG

GREEN

Report by Colin Watt for October 2024

This is a restricted project. Those with access will be able to view the October report on the project's website.

Link to secure report

Section Four: Closed or Withdrawn Projects 2023/24

Project Info.    Project Managers Commentary

 

 

 

Programme Status
RAG Status
Overall
AMBER
Has formal escalation taken place?
No
RAG Commentary
Overall Programme RAG status this month is AMBER.