Report for April 2015

Report Date
April 2015

Report compiled by Tim Gray (IS Apps Programme Manager) for Dawn Ellis (Programme Owner) 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects

Section Five: Actions/Notes from Current Meeting

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

In this reporting period the work has continued on both projects. EdWeb development is continuing well however the graphic design resource issue remains a concern. Steven Ross is now working on the project until the end of May, this should ensure that the key deliverables and preparation work for R5 will be completed. However for the period May to August no graphic design lead has yet been confirmed. A performance issue was during I21 and hot fix will be applied in early May. 

The migration project has made excellent progress with the Varnish process greatly improved. The performance issue noted above has resulted in the last batch of sites being pushed out by one week, however, this does not impact on forthcoming migrations.

In the next reporting period we will start to look at planing next year's programme.

RAG and Forward Look

Resources

The resources table below reflects numbers rounded to the nearest whole:

The table below shows a resource breakdown per team:

 

Note: Production Management time includes 60% FTE developing on UWP006

Section Two: Projects Not Started

Project InfoProject Manager's Commentary
Both this year's projects are now in flight.

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

UWP006 (AP34-045)

New University-wide Web CMS

Category: Funded

Milestones

15-May-2015Release 4 ReviewDeliver
31-Jul-2015Release 5 ReviewDeliver
08-Aug-2015Migration and Rollout ReviewDeliver
14-Aug-2015ClosureClose

RAG Status

GREEN

Report by Tim Gray for April 2015

Achievements in Last Period

  • Iteration 21 completed
  • Release 22 started
  • Revised JIRA processes for back log maintenance and feedback management implemented 

Issues

  • Graphic Design Lead resource has been secured until the end of May but ownership and the period between May and August remains an issue (Risk 16)

Next Steps

  • Complete iteration 22
  • Deploy release 4 to LIVE
  • Work on resolution to Graphic Design Lead role 
  • Prioritise stories for release 5
  • Continue to refine and maintain backlog 

 

 

UWP010 (AP45-031)

Drupal Migration

Category: Funded

Milestones

 

19-May-2015Release 3 Migration complete
08-Sept-2015Release 4 Migration completed
30-Sep-2015Release 5 Migration - Interim Progress Review
08-Dec-2015Release 5 Migration complete
15-Jan-2016Closure

RAG

GREEN

Report by Karen Stirling for April 2015

 

Achievements in Last Period

  • Release 3 - 4 JIRAs remaining to be resolved
  • Release 3 – 26 Sites are now LIVE – total number of sites migrated to date for project is 41
  • Release 3 – 17 sites to be migrated via STAGING to LIVE for being updated by the editorial teams / site owners
  • Release 3 - 18 sites to be URL switched on 19/05
  • Migration coordinator activities ongoing for Release 4
  • Release 4 – ongoing communications being issued out by Migration Liaison Officers to site owners in preparation for release 4 commencing on 01/06

Issues

  • Final sites delayed migration to STAGING due to issues encountered - hot fix being deployed via UWP006 this has been delayed due to Bamboo Upgrade
  • UAT VM Build ready for bamboo deployment plan to be completed - this has been delayed due to Bamboo Upgrade taking longer than expected out with project
  • Further review of URL Switch tasks following introduction of UWP resource available on site during switching and additional details provided via UNIDESK calls - Tech Man have advised happy with additional support and information provided by UWP. Agreement to review release 3 experience at end of migration release mid May. Tech Man agreed to be part of the migration team instead of this activity being placed with Dev Tech.

Next Steps

  • Resolution of remaining JIRAs
  • Preparation for early migration to Test for IS websites
  • Complete final 18 sites via STAGING / LIVE and URL Switch planned to be completed by 19th May (delayed by 1 week)
  • Complete release 3 review
  • On-going preparations for Release 4 activity
  • Complete work on UAT VM
  • Review project budget

 

The project status is GREEN

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

Project InfoProject Managers Commentary

AP34-066

New University-wide Web CMS

Category: Funded

This project was withdrawn on 29/08/14  (WIS Notes 29/08/14).

The project scope and budget have been incorporated into UWP006.

UWP009 (AP34-046)

Migration Preparation of Polopoly Content and Data Structures

Category: Funded

Report by Colin Forrest

Project was closed on 12/09/14 - Completion Report

 

 

Section Five: Actions/Notes from monthly meeting

ProjectAction / NotesResponsibilityStatus
    
    

 

Documentation