Report for May 2015
- Report Date
- May 2015
Report compiled by Tim Gray (IS Apps Programme Manager) for Dawn Ellis (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Actions/Notes from Current Meeting
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
In this reporting period both projects have achieved their next scheduled milestones. Despite performance issues on LIVE the migration project has successfully completed the 3rd migration phase. Although the migration phase has been completed, the remaining migration schedule is under review as it is clear that the current significant level of commitment to out of hours is not sustainable for a longer period of time. The CMS development work is now in it's final phase. In the last reporting period EdWeb Release 4 was successfully released. The graphic design risk noted for the past few months has been reduced as CAM have committed to complete all activities currently underway. For June we have a code and performance review scheduled by external consultants.
In June programme planning for 2015/16.
RAG and Forward Look
Resources
The resources table below reflects numbers rounded to the nearest whole:
The table below shows a resource breakdown per team:
Note: Production Management time includes 60% FTE developing on UWP006
Section Two: Projects Not Started
Project Info | Project Manager's Commentary |
---|---|
Both this year's projects are now in flight. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
Category: Funded Milestones
RAG Status GREEN | Report by Tim Gray for May 2015
Achievements in Last Period
Issues
Next Steps
| ||||||||
|
| ||||||||
Category: Funded Milestones (Under Review)
RAG GREEN | Report by Karen Stirling for May 2015 Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP34-066 New University-wide Web CMS Category: Funded | This project was withdrawn on 29/08/14 (WIS Notes 29/08/14). The project scope and budget have been incorporated into UWP006. |
Migration Preparation of Polopoly Content and Data Structures Category: Funded | Report by Colin Forrest Project was closed on 12/09/14 - Completion Report |
Section Five: Actions/Notes from monthly meeting
Project | Action / Notes | Responsibility | Status |