Report for August 2022

Report Date
August 2022

Section One: Commentary, RAG, and Resources Update

Programme Commentary

This year's programme has now kicked off with last year's Portal Services project containing. This will be a busy year for the programme, this will kick off in September with a workshop to decide how this year's core funded projects will be coordinated and run. 

RAG Status and Forward Look

Resources

Section Two: Projects to be Started

Project Information Programme Manager's Commentary
WPS014 - Annual Portal Service Upgrade 22/23 This project is scheduled to start in October 2022.
WPS015 - Notifications Service Upgrade This project is scheduled to start in September 2022.
WPS016 - EdWeb Decommissioning This project is scheduled to start in May 2023.
WPS017 Portal Services Continuous Improvement Project scheduled to start in October 2022.

Section Three: Projects in Progress

Project Info

Project Managers Commentary

WPS007 Design System

Discretionary

Milestones

Milestone Due Date
Sprint 21 06-Sep-22
Sprint 22 27-Sep-22
Release DS 0.2 16-Dec-22
Project closure

23-Dec-22

 

RAG

Green

Report by Chris Copner for August 2022

Achievements in Last Period

  • Sprint 21 started – this is also an IP iteration (#4)

  • 4th PI Planning session took place on 31st August

  • Decision taken to restart sprints on 7th September (sprint 22) – this takes into account feedback from previous PI planning sessions and planned annual leave during August
  • Work to complete the final stage of PI planning prior to recommencing sprints (on 7th Sep) is continuing – the Jira tickets will be created w/e 2nd Sep
  • Editorial Working Group - inaugural meeting took place on 9th August
  • Presentation of ILG to CAHSS took place 23rd Aug Presentation of ILG to MVM to be scheduled in Sep
  • Planning of DS 0.2 Jira tickets has started based on the previous PI planning sessions
  • Changes to Jira template reviewed with Scrum team
  • Purpose of Scrum ceremonies reviewed with team in order to look for opportunities to improve and optimise use of team members’ time
  • RFC Submission form drafted and uploaded to CAB Wiki page

Issues

  • None

Next Steps 

  • Scrum Master handover (scheduled 6th Sep)
  • Continue with Designathon next steps
  • Start video documentation for desktop Search Summary component
  • Analysis of Multibrand Checklist session to be completed and outputs reviewed by stakeholders attending the checklist session
  • Inclusive data gathering to be added to Editorial Working Group backlog
  • Start sprint 22

 

 

 

 

 

 

 

WPS008 Web Publishing Platform Implementation

Compliance

Milestones

Milestone Due Date
Release DS 0.1 12-Apr-2022
Project closure 23-Dec-2022

RAG

AMBER

Report by Bruce Darby for August 2022

 

 

Achievements this period

  • Web form bug fixes and improvements
  • Fixed deployment and update issues. Implemented new way of deploying code. 
  • Work still continues to replace the current 'Web Application'. This will support legacy applications.   
  • Working continuing on , Google Tag Manager module, Single Sign On Implementation
  • Testing JavaScript functionality
  • Return to School of Engineering (Drupal but non-EdWeb) migration.
  • Communication started with key stakeholders for the content migration schedule.
    • August Web publishers community event with about 60 attendees
    • Lead publisher list 95% complete
    • 100 sites have accepted their migration phase and their 2 week time slot.
  • Work on local navigation and global navigation continues 
  • Training outline structure built in Wiki and training and support materials ongoing. 
    • Training dates now set for: Thursday 1 September 
    • Training and video guidance continues - web form tutorial started

Issues

  • Still some issues with deployment and migration process which could effect dates of sites going live.  
    • Project to stay Amber
    • Contingency built in as there are no plans for site migration during September 2022
    • Decided to pause the migrations for a short period and so will need to reschedule 5 sites which were due to go live due to some migration process issues. 
      • Content we don't want to migrate still migrating
      • Image permission issues
      • URL not formating correctly
  • TPXimpact have stepped back as planned but this has slowed work as we adjust to this. 
  • Project team reduced due to long term illness of one member - update now returned to work. 
  • UX Manager left in August. Recruitment process started

Next steps

  • Use of taxonomies to create grouped content on listing pages
  • Requirements for possible Postgraduate Research Opportunities content type

WPS010 Personalisation within Portal

Discretionary

Milestones

Publish school portlet 08-Sep-2021
Discuss results with school colleagues 28-Feb-2022
Create content guidelines 31-July-2022
Establish backlog/roadmap detail for devolving personalisation 31-Jul-2023

RAG

GREEN

Report by Mary Elder for August 2022

Achievements in last period

  • Two pilots for 2022/2023 identified.

Issues

  • Problems have been identified with the maintenance of the POS code data in MyEd which will delay one of the pilots.
  • The milestone relating to devolving content management has been moved out by a year, as the one pilot we have run didn't provide enough information for us to take this forward, and we'll need to do further research.

Next Steps

  • Continue planning for 2022/2023.
  • Further investigation into POS Code issues. 

 

 

WPS012 Annual Portal Services Upgrade

Discretionary

Milestones

Assessment for Google Analytics 05-Sep-2022
Google Analytics 4 implemented on MyEd Dev 12-Sep-2022
Google Analytics 4 implemented on MyEd TEST 19-Sep-2022
React upgrade - DEV complete 03-Oct-2022
React TEST upgrade: integration complete 14-Oct-2022
React - UAT Complete 21-Oct-2022
React Upgrade to LIVE 26-Oct-2022
Google Analytics 4 implemented on MyEd LIVE 02-Nov-2022
Deployment Sign Off Review 11-Nov-2022
Closure 18-Nov-2022

RAG

AMBER

Report by Chris Konczak for August 2022

Achievements this period

  • No progress or achievements were made this period as developer and other project team members were on annual leave until 15th August. The project team agreed that there would be no work carried out until their return.

Issues

  • On the developer's return they were not able to complete the analysis for Google Analytics as they were requested to help on P&M for testing bug fixes and for go-live. This has put WPS012 approximatively two weeks behind where we should be. Google Analytics 4 analysis and implement to DEV and TEST should have been completed.  Resourcing has been re-assigned and secured to complete Google analytics 4 and React upgrades.

Next steps

  • Analysis for Google Analytics 4 to be completed
  • Google Analytics 4 to be deployed to DEV and TEST
  • React upgrade to DEV to commence

 

RAG Commentary
Due to P&M go-live, the developer had been conflicted to work on this from their return from annual leave on 15/08 resulting in no progress on WPS012 during August. This has now been resolved with work on Google Analytics starting form 01/09. Resourcing is assigned. Impact: a two week delay for the project with deployment and closure milestones extended.
 

Section Four: Closed or Withdrawn Projects 2022/23

Project Info Project Managers Commentary

 

 

 

 

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?
No