Build

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 0.0 days 0.0 days 0.0

The  managed infrastructure replacement cycle provides a managed approach to investment and cost management. Sustained investment in computational and data infrastructure underpins UoE competitiveness (as outlined in the University Strategy).

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 45.0 days 52.0 days 8.0

The RSS compute and storage  infrastructure underpins all computational and data based research activities in UoE. All infrastructure hardware has a finite defined maintenance lifetime. A typical supported lifetime for server and storage hardware is 5 years (the majority of vendors will not supply maintenance for longer periods). University of Edinburgh research infrastructures have been operating in a “rolling refresh” model for the last 5 years.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 80.0 days 45.0 days 35.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2021 GREEN 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
September 2021 GREEN 0.0 days 0.0 days 0.0

The project will aim to deliver:

 1. Data futures requirements gathering (HESA’s transformation programme to deliver a more efficient data collection process); this work will enable an understanding of what is required to meet the requirements of the new HESA return, address the system design options and how Tribal software can be best used to capture data. Aim is to capture all the requirements and prioritise them.

 2. This will inform and prioritise the system and process changes:

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 AMBER 0.0 days 0.0 days 0.0

Storage Manager Operational Transition

This project will take the updated and improved Storage Manager code created in RSS035 and create the back-end connections and scripts that are required to link the new code to the RSS systems.

This will allow the new code base to be used in parallel with the existing system to verify correct behaviour.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 171.5 days 118.9 days 52.6

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2022 GREEN 0.0 days 0.0 days 0.0