Close

 This project will confirm the Terms of Reference and the Business Requirements for three separate project proposals:  

AP12-003 (FIN) - PAYE AP23-005 (HRS) - HR Tax Year End 12/13 AP23-007 (HRS) - Real Time Tax Year End / Real Time Information

A follow-on 2012-13 project, under the HR-Payroll programme, will then take the agreed requirements forward to the technical stages and deployment.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2012 BLUE 18.0 days 11.2 days 0.0

Project Summary:

 

Contributors

 

 

Role

Department

Name

Project Manager (Owner)

IS Apps Project Services

Jamie Thin

Programme Manager

IS Apps Project Services

Jamie Thin

Production Management Coordinator

IS Apps Apps Mgmnt

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2012 BLUE 0.0 days 0.0 days 0.0

                                                                                      

 This project will deliver timesheet functionality required by both HTBN staff and Research staff involved in Framework 7 (FP7) and Research Council funded projects.

This will be delivered through a phased approach:

Analysis (complete): 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2012 BLUE 628.0 days 619.0 days 0.0

 

 

To deliver small-scale enhancements to the EUCLID student record system application (Internally driven by process improvement)

this will be delivered in multiple phases , each phase will have its own business requirements document (BRD) written by SACS Registry,

IS Apps will deliver SITS configuration to meet the business requirements.

 

This project will be delivered in multiple phases , each phase will have its own BRD and milestones into TEST and LIVE.

 

Update 6-Feb 2013

Project closed  

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2013 BLUE 259.0 days 259.0 days 0.0

Project Summary:

The objectives for achieved under this project are:

Please note that this project has been carried over from the Old Projects website.information pre 6 August 2012 can be found at http://www.old.projects.ed.ac.uk/areas/learn/eca_lms/ECA001/index.shtml

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2013 BLUE 0.0 days 0.0 days 0.0

 

AP12 040

The annual HESA and SFC returns are statutory and key to UoE obtaining funding from bodies such as SFC.

This project will incorporate Student Funding Council (SFC), Teaching Load (TL) and Student HESA Returns for 2011-12, all under AP12-040. STU211 will run from September 2011 until December 2012. (The OLL HESA Return will be handled by another project under AP12-038 OLL HESA 11-12 and will run for a much shorter time-scale.)

This Project has been allocated 80 days in annual planning to cover the Statutory Returns

 

SAAS have introduced a requirement for HEIs to confirm student attendance and to notify SAAS of Changes in Circumstances via file interaction.  SAAS’s requirements were finalised late and have flaws. SAAS has subsequently confirmed that HEIs can phase implementation – student attendance and withdrawals must be notified via the file process for 11/12, change of circumstances for 12/13.

 

The Oracle SOA suite was chosen as one of our key enabling technologies for enterprise application integration and developing agile business processes. Currently, several key applications have been developed on the Oracle SOA 10g suite, including the new Identity Management system (IDM) and Infinite. Oracle released a major new version of SOA, 11g and the final 10g development release was issued in September 2009.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2013 BLUE 334.0 days 334.0 days 0.0