Project Summary:

1) UoE successfully completed KIS Return for 2012/3 (C12061) and 2013/4 (C13061) and thus meet the relevant HEFCE statutory regulations.  

2) Facility now exists in EUCLID CCAM for Schools to capture Breakdown of Assessment for each Course.

ABS have advised that eExpenses will be de-supported from 12/13 and the University will urgently require a replacement for this service. The purpose of this project is to identify the best way forward for the University over the next 3-5 years. Then having identified the solution the project will implement the recommended option.

The Project will deliver an electronic expenses solution for the University which could be delivered via a number of options e.g. by replacing eExpenses or adopting the ABS software, or purchase of alternative software or in-house solution.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2014 BLUE 0.0 days 0.0 days 0.0

 

This project will develop a set of tools to support the research for a project being developed by the school of economics to investigate how people search for work (jobs) and the incentives used to do that.  The project will take a feed of data from the Department of Work and Pensions and use this as the basis for the research.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2014 BLUE 0.0 days 0.0 days 0.0

Project Summary:

Background

Were the project goals met?   Yes

Were the project deliverables fully or partially accomplished?  Partially another project will be started to deliver the remaining scope.

The goals of the projects were:

The purpose of the project is to review Direct Admissions Processes across the university with a particular focus on PG and VS applicants looking at the process from the decision to submit an application to the point of decision.  This review will be facilited by an external consultant who will cover the following areas as part of the review:

  • Current Business Processes
  • EUCLID Software/Other Software usage
  • Policies and Guidelines
  • Possible Future Business Processes

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2015 BLUE 382.0 days 394.0 days 1.0

Project Summary:

 

Contributors

Role

Department

Name

Date

Project Manager (Owner) & Programme Manager

IS Apps / project services 

Franck Bergeret

17/12/13

Developer

IS Apps / SSP IS

Peter Pratt

Project Summary:

 

Contributors

 

 

Role

Department

Name

Project Manager (Owner)

 

 

Programme Manager

 

 

Production Management Coordinator

 

 

Business Area Manager  

 

 

Project Summary:

  • RES037 – 3 outstanding jiras from RES037 to be put live under the scope of RES049 (they were RES037-289, RES037-283 and RES037-288). These went live on 29 August 13.

 

  • Only those JIRAs identified in RES037 as needing completion were in scope for RES049. They were the jiras that were considered a lower priority when completing issues in RES037 but to allow closure of RES037 they were to be completed under RES049. The jiras are:

 

 

PURE Enhancements

 The Pure Enhancements project whas been created to complete the outstanding JIRAs from RES037 (Implementation of PURE Publications Service).

 

 

JIRA: https://www.jira.is.ed.ac.uk/jira/browse/RES049

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2014 BLUE 38.0 days 34.3 days 0.0