Close
Project Summary:
The objectives for achieved under this project are:
Please note that this project has been carried over from the Old Projects website.information pre 6 August 2012 can be found at http://www.old.projects.ed.ac.uk/areas/learn/eca_lms/ECA001/index.shtml
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2013 | BLUE | 0.0 days | 0.0 days | 0.0 |
AP12 040
The annual HESA and SFC returns are statutory and key to UoE obtaining funding from bodies such as SFC.
This project will incorporate Student Funding Council (SFC), Teaching Load (TL) and Student HESA Returns for 2011-12, all under AP12-040. STU211 will run from September 2011 until December 2012. (The OLL HESA Return will be handled by another project under AP12-038 OLL HESA 11-12 and will run for a much shorter time-scale.)
This Project has been allocated 80 days in annual planning to cover the Statutory Returns
SAAS have introduced a requirement for HEIs to confirm student attendance and to notify SAAS of Changes in Circumstances via file interaction. SAAS’s requirements were finalised late and have flaws. SAAS has subsequently confirmed that HEIs can phase implementation – student attendance and withdrawals must be notified via the file process for 11/12, change of circumstances for 12/13.
The Oracle SOA suite was chosen as one of our key enabling technologies for enterprise application integration and developing agile business processes. Currently, several key applications have been developed on the Oracle SOA 10g suite, including the new Identity Management system (IDM) and Infinite. Oracle released a major new version of SOA, 11g and the final 10g development release was issued in September 2009.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2013 | BLUE | 334.0 days | 334.0 days | 0.0 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
February 2013 | BLUE | 0.0 days | 0.0 days | 0.0 |
This project is to upgrade the existing Oracle database owned by the University Web Site Team, POLO, from Oracle 9.2 to 10.2.
The current version of the Oracle POLO DEV, TEST and LIVE databases is 9.2. Oracle 9.2 is past its Extended Support date. The three POLO databases should be upgraded to lower the cost to the University, to mitigate security issues and to enable the business owner to take advantage of new features which IS have currently implemented (SOA) and which IS will implement in the future.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
September 2012 | BLUE | 0.0 days | 0.0 days | 0.0 |
Project Summary:
The Campus Maps application was identified as one of the worst offenders of placing privacy invasive cookies on users machines. The application was upgraded to use v3 of Google Maps which does not store privacy invasive cookies.
Analysis of Resource Usage:
Staff Usage Estimate: 24.5 days
Staff Usage Actual: 25.5 days
Staff Usage Variance: -4.08163%
Other Resource Estimate: 1 days
Other Resource Actual: 1 days
Other Resource Variance: 0%
The‘cookie law’ (Privacy and Electronic Communications Regulations) is a piece of privacy law that requires websites to obtain consent from visitors to store or retrieve any information on a computer. It is intended to protect online privacy, by making consumers aware of how information about them is collected by websites, and enable them to choose whether or not they want to allow it to take place.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
October 2012 | BLUE | 24.5 days | 26.0 days | 0.0 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
July 2013 | GREEN | 83.0 days | 73.0 days | 0.0 |