Close

Extract and reports from Unidesk data

Project Summary:

Objectives

The primary objective of the project was to upgrade the POLO database to version 10g of Oracle. This was achieved.

Deliverables

 The deliverables of the project were as follows

This is a small-scale enhancement as a sub-project of SAC003.

- for the overall project SAC003, see

https://www.projects.ed.ac.uk/project/sac003

Update 7-Nov 2012

E2 - UKBA - Length of Tier4 Study in UK - deployed to LIVE on 06-Nov 2012

 

 

 

Development of web services to extract data from PURE into School websites will help to cement PURE’s role as the University’s record of its research activity, moving to remove duplication of effort and records.

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2013 BLUE 21.0 days 19.0 days 0.0

 

Following the completion of Phase 1 of the RMAS project, the Project Board have approved the Business Case.  The following will now be undertaken:

The Procurement phase will be postponed until January 2013, to enable:

 

A. Detailed analysis of post award processes and systems to be done with Finance teams (RGS and FIS).  This will be re-tested against the post-award needs raised by the various stakeholder groups.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2013 BLUE 0.0 days 0.0 days 0.0

 

additional components for the Programme Management (until these enhancements are made to the projects web site)

Project Summary:

Analysis of Resource Usage:

Staff Usage Estimate: 1 days

Staff Usage Actual: 1 days

Staff Usage Variance: 0%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

Key Learning Points:

Outstanding issues:

 

additional compoenents for the Programme Management (until these enhancements are made to the projects web site)

Project Summary:

Analysis of Resource Usage:

Staff Usage Estimate: 1 days

Staff Usage Actual: 1 days

Staff Usage Variance: 0%

Other Resource Estimate: 1 days

Other Resource Actual: 1 days

Other Resource Variance: 0%

Explanation for variance:

Key Learning Points:

Outstanding issues: