Project Summary:
This project implements the new Learn software from supplier Blackboard that replaces WebCT, the universities centrally supported VLE.
This project is carrying over from 2011/12, and all project information prior to August 2012 is available from
http://www.old.projects.ed.ac.uk/areas/learn/general/LAT010/index_table.shtml
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
August 2012 | BLUE | 740.0 days | 760.0 days | 0.0 |
Project Summary:
Contributors
Role | Department | Name |
Project Manager (Owner) | IS Applications - Project Services | Tim Gray |
Since the current document management set was implemented at the University, Kofax have revamped Ascent Capture (now version 10) and introduced a new licensing module as well as a server based administration. This project involves setting up a Kofax server from which the individual scan units can be much easier administered and the scan volume is controlled from a central pool. Any changes to document batches can be completed on the server and pushed out to the individual scan PCs.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2012 | BLUE | 49.0 days | 46.9 days | 2.0 |
Project Summary:
The original objectives and deliverables for this project were:
OBJECTIVES
- To migrate the Student Tracking, and SAGE applications to ColdFusion 9
- To update supporting technical documentation for the migrated application
DELIVERABLES
This project will migrate the following Careers applications - Student Tracking, SAGE and DLHE - to ColdFusion 9 as v6 will no longer be supported from later this year.
The Business Objectives are:-
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
September 2012 | BLUE | 44.0 days | 47.7 days | 0.0 |
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
April 2013 | BLUE | 62.5 days | 33.8 days | 1.0 |
This project will create new TEST and TRAINING environments for the Accommodation Services critical business application 'Kx'. The focus of the project will be to:
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2012 | BLUE | 0.0 days | 0.0 days | 0.0 |
Background
The current Polopoly search has limited functionality and isn’t easy to use, as such it needs to be improved in a number of areas.
The search features are spread over a number of different tabs. All searches cover all content (of certain type) within the system and there is no way to filter results for content within specific sections of the system. Users cannot search articles, sections and media bank resources at the same time. The main ‘Search’ tab has three options available through the following tabs:
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
December 2013 | BLUE | 35.0 days | 37.9 days | 0.5 |
This project will deliver an Interface which will transfer the Lease Sales Invoice information to the appropriate eFinancials Sales Ledger (via CLINK). The Interface will also post back to Archibus that the invoices have been sent to eFinancials.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
January 2013 | BLUE | 0.0 days | 0.0 days | 0.0 |