Deliver

Note: There is an understanding that any technical parts to the solutions will be procured from an external 3rd party vendor. To this end, there is an underlying design principle that the technical functionality will not be configurable, and will be used “off the shelf”.

There may be a “chicken and egg” situation, in that we cannot determine how we need to work, and therefore define the requirements, until we understand what technical functionality will be procured. And we cannot determine the technical functionality until we have reviewed how we want to work.

Background

The use of space within the College of Arts, Humanities and Social Sciences has become a pressing priority in the majority of Schools. For a small number of Schools, it is such an issue that the need to manage space systematically has emerged, whereby staff can manage multi-occupancy rooms more efficiently and transparently. A workshop was conducted on Wednesday the 1st of March 2017, to help further understand the As- Is process. The details from that workshop have been added below

 

 

Contributors

 

Role Organisation Name Date Signed Off

Production Management Coordinator (Owner)

IS Apps

Stuart Craig / Brian Denhom

 

Project Manager

IS Apps

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2018 GREEN 0.0 days 0.0 days 0.0

To be updated with new broader objectives. 

 

Project document: Fairtrade Universities pilot

Background

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2020 GREEN 0.0 days 0.0 days 0.0

Project document: Make ICT Fair - reforming manufacture and minerals supply chains through policy, finance and public procurement

Background

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2020 GREEN 0.0 days 0.0 days 0.0

Developing and implementing APUC Sustain supplier monitoring database

Background

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2020 AMBER 0.0 days 0.0 days 0.0

Project document: title

Background

To add (include link with potential work on Sustain; and maintain link with SPPT and Sustainability Test Tool progress)

 

Scope

Main project: To add

Work stream 1: SRS Supplier Engagement Internship

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2019 GREEN 0.0 days 0.0 days 0.0

This project supports the delivery of the Sustainable Campus Fund from the Department for Social Responsibility & Sustainability

Background

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2020 AMBER 0.0 days 0.0 days 0.0

Project document: Developing our Living Lab approach

Background

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 GREEN 0.0 days 0.0 days 0.0