Design

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2024 AMBER 0.0 days 0.0 days 0.0

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2024 GREEN 0.0 days 0.0 days 0.0

The project will deliver a new central web provision for prospective students, replacing the existing undergraduate and postgraduate degree finders, and the EdWeb-driven websites under www.ed.ac.uk/studying.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2024 GREEN 0.0 days 0.0 days 0.0

Joesph Black - T150 and T250.

PTZ upgrades.

Control System upgrade to show Echo audio levels

Control system upgrade to pause recording if we swap out the old Delcom lights

(Projector install)

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2024 GREEN 0.0 days 0.0 days 0.0

This is a redevelopment of level 2 in the Chancellors Building. There is only 1 room that has been identified as requiring AV and will cost less than £20K plus VAT.

 

At this point I have limited information about the project and am awaiting a PoW.

 

Estates contact: Katharine Isherwood (EDM)

Current work in progress:

Draft Library Dashboard (ed.ac.uk)

 

Stage 1 - 

Using Alma api analytics output to build a dynamic webpage to raise the profile of the library overall.

Requirements:

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2021 GREEN 0.0 days 0.0 days 0.0

The Technical Architecture Document (TAD) can be found here:

dsg\Projects\EST081