Project journal

Title Description Author Post date
Second set of workshops completed - ready for Design

 

 

February has seen two sets of workshops, with Softcat meeting key folk from all the UOE stakeholders - colleges, ITI, Apps, LTW and USD.

Softcat have most of the information needed to now move onto design and refine the plan, so we can book the UoE resources needed

Plenty of follow up actions but project progressing well

 

Project Board meet on 11th April

 

Maurice Franceschi 24-Feb-2017
Consultancy being sought

Graham currently exploring best way to secure a specialist consultant who can come in, get the requirements and recommend the right technical solution.

Crown Office is one route,

 

 

Maurice Franceschi 18-Feb-2016
January Update

A programme planning day was scheduled for the 18th, which set out dates for DTP001 and the other projects, many of which interact with each other.

 

It is clear now that the team doe snot have the expertise to move the project onto the next stage of analysis and design - Graham is recourcing a specifialist consutlant

Maurice Franceschi 08-Jan-2016
December update

 

With R&D mostly done, and discussions with colleges also helping to clarify needs, we will be starting the project and moving to Planning phase early January

Maurice Franceschi 18-Dec-2015

Project Info

Project
Apps Ed
Code
DTP001
Programme
ITI - Desktop Services (DST)
Management Office
ISG PMO
Project Manager
Gail Devaney
Project Sponsor
Anthony Weir
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-Oct-2015
Planning Date
29-Apr-2016
Delivery Date
03-Feb-2020
Close Date
04-Nov-2020
Overall Priority
Normal
Category
Compliance