Second set of workshops completed - ready for Design |
February has seen two sets of workshops, with Softcat meeting key folk from all the UOE stakeholders - colleges, ITI, Apps, LTW and USD. Softcat have most of the information needed to now move onto design and refine the plan, so we can book the UoE resources needed Plenty of follow up actions but project progressing well
Project Board meet on 11th April
|
Maurice Franceschi | 24-Feb-2017 |
Consultancy being sought |
Graham currently exploring best way to secure a specialist consultant who can come in, get the requirements and recommend the right technical solution. Crown Office is one route,
|
Maurice Franceschi | 18-Feb-2016 |
January Update |
A programme planning day was scheduled for the 18th, which set out dates for DTP001 and the other projects, many of which interact with each other.
It is clear now that the team doe snot have the expertise to move the project onto the next stage of analysis and design - Graham is recourcing a specifialist consutlant |
Maurice Franceschi | 08-Jan-2016 |
December update |
With R&D mostly done, and discussions with colleges also helping to clarify needs, we will be starting the project and moving to Planning phase early January |
Maurice Franceschi | 18-Dec-2015 |