Completion Report

Project Summary:

Objective 

The objective stated at the outset of the project was to:

Provide a solution that upon single site or server hardware failure reduces the time to recover the web-tier.  In addition the revised infrastructure must be proven through load testing to not degrade web-service response times

Completion Notes:

- The project has met the original objective through the utilisation of Virtual infrastructure technology. Deliverables

Deliverable (strategy document covering the following items)DeliveredNotes
Identify available solutionsY 
Evaluate available solutionsY 
Plan performance and availability testing (measurements and metrics)PartialAutomated testing initially thought this possible but would have required significant additional effort. A decision was taken that given the vertical scaling capacity of VEEAM, additional resource could be deployed in event of any performance issue.
Execute performance testing against current Test infrastructureY 
Introduce chosen solution to Test infrastructure and re-execute test planY 
Compare performance of new Test environment against 'old'Y 
Decide whether solution meets business need or whether to adopt alternative solutionY 
Introduce solution to Production environmentY 

Phase 2 deliverables (postponed until further notice)

1.   Configure load balancer for Test 2.   Configure load balancer for Production

 

Benefits

As stated in the Project Brief the project benefit would result from alignment of a priority 1 service with the University goal to provide quality services through the development of the underlying technical architecture.

The primary objective was to reduce the time to recover webservices in event of loss of infrastructure or components.  This time has been reduced from an estimated 2 days to 1 hour during IS business hours.

Analysis of Resource Usage:

Staff Usage Estimate: 56 days

Staff Usage Actual: 25 days

Staff Usage Variance: -55%

Other Resource Estimate: 0 days

Other Resource Actual: 0 days

Other Resource Variance: 0%

Explanation for variance:

Project estimation varied throughout the project as various solutions were considered.  The chosen solution did not require the development originally anticipate as this work had already been completed by IS Architecture through their deployment of VEEAM.

Key Learning Points:

Outstanding issues:

There are no outstanding issues.  Operational documentation has been updated with information arrising from testing.

Project Info

Project
Resilient Web applications tier for Kx infrastructure
Code
ACS031
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Iain Dobson
Project Sponsor
Claire Barnish
Current Stage
Close
Status
Closed
Start Date
12-Nov-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
02-Apr-2014

Documentation

Close