Report for February 2019

Report Date
February 2019

Achievements in the last period

  • Application Webservers
    • Load Balancing testing was successfully completed, including resilience testing 
    • The migration to the new Application Servers is scheduled to be completed w/c 11th March and in preparation
      • Implementation plan has been prepared and signed-off by the project team 
      • Service alert has been prepared and published 
      • Request to Change Control Board 
      • Deployment checklist has been commenced 
      • The build of the live Application Webservers have been completed 
      • Commenced review of load balancer configuration on the live servers 
  • Database Servers 
    • The build of the database servers has continued, but there is still the requirement to create users before handing over to KSL 

Issues

  • During the testing via the load balancers, it has been discovered that some of the windows services cannot be run on simultaneously on both Application Webservers, such as BedBooker and Call Logging.  Investigations are on-going to determine if these services can be run within a cluster on the Database server.  If this proves not to be possible, there may the requirement to accept that such services will require only to be run on a single site 
  • It has also become apparent that it is not possible to test all aspects of the live system on Test.  This relates to BedBooker and Call Logger
  • the proposed Live changes regarding student contracts have been delayed and this could impact on the UAT of the new database servers 

Next steps

  • Application Webservers
    • Deploy to live via the Load Balancers 
  • Database Servers 
    • Complete build of new test Database servers 
    • Complete User Acceptance Testing 
  • Windows services 
    • Requireemnt to review remaining windows services 
  • Technical Documentation 
    • Update Technical Architecture Document
  • Live Deployments 
    • Determine requirements regarding live operational changes that require to be implemented and ensure any such changes does not impact on the on-going Test environment 
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Whilst Phase 1 of the project (Delivery of Application webservers) is currently planned for 13th March, this could be delayed if an agreeable resilient solution to the window services is not forthcoming. For Phase 2 (Database servers), there is also a concern regarding the delay of the student contract changes, as this could impact on the timescales for the UAT of the database servers
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
10.9 days
Activity this year
59.7 days
Activity to date
59.7 days
Estimate to complete current year
37.4 days
Estimate to complete future years
0.0 days

Project Info

Project
KX Infrastructure Upgrades
Code
ACS041
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Claire Barnish
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
29-Aug-2018
Planning Date
28-Sep-2018
Delivery Date
29-Mar-2019
Close Date
28-Jun-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary