Report for August 2024
- Report Date
- August 2024
Achievements This Period
- All resource requests now raised for all required IS technical teams based on original estimate
- Further planning meetings held and high level plan agreed
Issues
- None
Impact
- None
Next Steps
- Agree high level milestones
- Commence pre-migration activities
- Completed project brief
- Move to plan stage
- Complete Kinetics hosting assessment
Milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Initiate | Start | 02-Sep-2024 | No date available | No | |
Plan | Planning (Major) | 30-Oct-2024 | No date available | No | |
Build | Complete build of Test | 20-Dec-2024 | No date available | No | |
Accept | UAT Completed | 31-Jan-2025 | No date available | No | |
Build | Completed build of live environment | 14-Mar-2025 | No date available | No | |
Accept | UAT of live environment | 24-Mar-2025 | No date available | No | |
Deliver | Go live | 04-Apr-2025 | No date available | No | |
Deliver | De-commission old services | 17-May-2025 | No date available | No | |
Close | Close | 30-May-2025 | No date available | No |
- Approved budget
- 100.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 100.0 days
- Estimate to complete future years
- 0.0 days