Report for August 2024

Report Date
August 2024

Achievements This Period

  • All resource requests now raised for all required IS technical teams based on original estimate
  • Further planning meetings held and high level plan agreed

Issues

  • None

Impact

  • None

Next Steps

  • Agree high level milestones
  • Commence pre-migration activities
  • Completed project brief
  • Move to plan stage
  • Complete Kinetics hosting assessment

Milestones

Stage Milestone Due Date Previous Date Complete  
Initiate Start 02-Sep-2024 No date available No

 view

Plan Planning (Major) 30-Oct-2024 No date available No

 view

Build Complete build of Test 20-Dec-2024 No date available No

 view

Accept UAT Completed 31-Jan-2025 No date available No

 view

Build Completed build of live environment 14-Mar-2025 No date available No

 view

Accept UAT of live environment 24-Mar-2025 No date available No

 view

Deliver Go live 04-Apr-2025 No date available No

 view

Deliver De-commission old services 17-May-2025 No date available No

 view

Close Close 30-May-2025 No date available No

 view

Project Status
RAG Status
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
100.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Kx Migration to Cloud
Code
ACS048
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
John Dawes
Project Sponsor
Carina Svensen
Current Stage
Build
Status
In Progress
Project Classification
Transform
Start Date
01-Sep-2024
Planning Date
19-Nov-2024
Delivery Date
04-Apr-2025
Close Date
30-May-2025
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation