Status report for April 2016
- Report Date
- April 2016
Achievementts this period
- Personas expanded to include resourcing requirements
- Met with Service Management to review Office365 capabilities and licencing arrangements
- Sourced & watched webinar of Project Online to understand product capabilities
- Shortlist of 4 suppliers drawn up
Issues
- Issues securing time with project resources due to higher priority project work (for project manager) and studies (for student)
Next steps
- Finalise stakeholders
- Arrange supplier demos
- Online survey of requirements
| Target date | Title |
|---|---|
| 15-Apr-2016 (overdue) | Website stakeholders identified |
| 29-Apr-2016 (overdue) | On-line survey created |
| 31-May-2016 | Supplier demos complete |
| 29-Jul-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days