Report for June 2016
- Report Date
- June 2016
Achievements this period
- Invitation to quote sent out to shortlisted suppliers
- Bids received from 3 of the 4 suppliers and initial review taken place. Clarifications needed on cost.
Issues
- Project Manager and Project Sponsor lack of availability continues to be a concern. This lack of availability is delaying the timeline.
- Project Sponsor to clarify funding position now that the project will be spanning into 16/17
Next steps
- Clarify supplier costs
- Complete stakeholder mapping
- Appoint supplier
Target date | Title |
---|---|
22-Jul-2016 | Website stakeholders mapped |
22-Jul-2016 | Supplier selected |
12-Aug-2016 | Prototype complete |
19-Aug-2016 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 1.0 day
- Activity this year
- 15.0 days
- Activity to date
- 15.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 9.0 days