Project review

Report Date
May 2016
  • Further planning meetings took place to:
    • review assigned actions
    • confirm timelines for delivery
  • Code sprint date confirmed for 14 July 2016. Invitations to relevant audiences and groups have been sent.
  • Preparation and support material agreed and started to be prepared.
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EdWeb code sprint
Code
API019
Programme
Z. IS Innovation - Applications (API) - Closed
Project Manager
Stratos Filalithis
Project Sponsor
Simon Marsden
Current Stage
Close
Status
Closed
Start Date
28-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a

Documentation