Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2017 July 2017 BLUE
Report for June 2017 June 2017 GREEN GREEN GREEN BLUE
Report for May 2017 May 2017 AMBER GREEN GREEN AMBER
Report for April 2017 April 2017 AMBER GREEN GREEN AMBER
Report for March 2017 March 2017 GREEN GREEN GREEN GREEN
Report for February 2017 February 2017 GREEN GREEN GREEN GREEN
Report for January 2017 January 2017 GREEN

Project Info

Project
Devops : IS Working Methods and Automation
Code
API020
Programme
Z. IS Innovation - Applications (API) - Closed
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
25-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017
Category
Discretionary