Report for May 2017
- Report Date
- May 2017
Achievements this period
- none
Issues
- Due to conflicts with higher-priority projects, team lead had not had the time to devote to the project as had been expected.
PM will hold a meeting asap in May to resolve this within the team, if the conflict cannot be resolved within ITI.
Target next period
- sign-off of requirements
- plan and resourcing of build and test
Budget Information
Budget | Breakdown | Spend to End of April 2017 | Total Predicted Spend | |
---|---|---|---|---|
£ 18,500 |
Staff Days £18,500 |
£ 5,177 |
£11,377 |
Budget forecast
Spend February | £2,480 | |
---|---|---|
Spend March | £930 | |
Spend April | £155 | |
Spend May | £ 1,612 | |
Estimated Spend June | £ 3,100 | |
Estimated Spend July | £ 3,100 | |
Estimated Spend August | £ xxx | |
Estimated Spend 17/18 | £ xxx | |
Total |
£ xxx |
- Approved budget
- 60.0 days
- Activity this month
- 4.2 days
- Activity this year
- 15.7 days
- Activity to date
- 15.7 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days