Report for June 2017

Report Date
June 2017
Achievements this period

 

  • migration from other versioning systems and testing - achieved
  • checking requirements are met - achieved
  • documentation - achieved
  • confirm deliverables achieved and not achieved - achieved
  • confirm benefits and lessons learned and closure report - achieved
  • set out what project would recommend for new service for ISG and UoE - achieved    
Issues
  • none  
Target next period
  • closure approval by WIS  
Budget Information
Budget    Breakdown  Spend to End of April 2017    Total Predicted Spend  
£ 18,500

 Staff Days £18,500

  £ 7,502

  £10,000

 

 

Budget forecast
Spend February    £2,480  
Spend March       £930  
Spend April       £155  
Spend May  £ 1,612
Spend June  £ 2,325
Estimated Spend July  £ 2,500
Estimated Spend August     £         0
Estimated Spend 17/18  £        0
Total

 £ 10,002

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
RAG Commentary
Project Delivery pushed back to late July as requirements finalisation and sign-off needs one more meeting and iteration.
Change Status
Activity
Approved budget
60.0 days
Activity this month
4.2 days
Activity this year
15.7 days
Activity to date
15.7 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Devops : IS Working Methods and Automation
Code
API020
Programme
Z. IS Innovation - Applications (API) - Closed
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
25-Oct-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Aug-2017
Category
Discretionary

Documentation