Report for June 2017
- Report Date
- June 2017
Achievements this period
- migration from other versioning systems and testing - achieved
- checking requirements are met - achieved
- documentation - achieved
- confirm deliverables achieved and not achieved - achieved
- confirm benefits and lessons learned and closure report - achieved
- set out what project would recommend for new service for ISG and UoE - achieved
Issues
- none
Target next period
- closure approval by WIS
Budget Information
Budget | Breakdown | Spend to End of April 2017 | Total Predicted Spend | |
---|---|---|---|---|
£ 18,500 |
Staff Days £18,500 |
£ 7,502 |
£10,000 |
Budget forecast
Spend February | £2,480 | |
---|---|---|
Spend March | £930 | |
Spend April | £155 | |
Spend May | £ 1,612 | |
Spend June | £ 2,325 | |
Estimated Spend July | £ 2,500 | |
Estimated Spend August | £ 0 | |
Estimated Spend 17/18 | £ 0 | |
Total |
£ 10,002 |
- Approved budget
- 60.0 days
- Activity this month
- 4.2 days
- Activity this year
- 15.7 days
- Activity to date
- 15.7 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days