Report for July 2018

Report Date
July 2018

Achievements

  • Planning for Drupal 8 code sprint on 2nd August.
  • Participation in Drupal 8 code sprint.

Issues

  • None

Next Steps

The second Drupal 8 code sprint contribution day has now taken place. All that remains is the final write-up and project closure.

  • Final write-up following Drupal 8 code sprint.
  • Project closure anticipated mid-August.

Budget Information

  • Spend to date £1160
  • Forecast to spend to date £3,880
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Code sprints for all the things
Code
API029
Programme
Z. IS Innovation - Applications (API) - Closed
Management Office
ISG PMO
Project Manager
Mairi Fraser
Project Sponsor
Jennifer Milne
Current Stage
Close
Status
Closed
Start Date
01-Dec-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
28-Feb-2019
Overall Priority
Normal