Container investigation work started by Development Technology. Presentation to Applications Division staff on containers arranged for Friday 13th April.
Issues
Industrial action resulted in booked tasks only partially being carried out. DevTech Bookings have been re-scheduled and assigned for first 2 weeks of May.
Next Steps
Continue with prototype build
Budget Information
The project spend to date is 1 days with 19 days remaining budget.
An additional 15 days have been assigned or requested, the total expected spend will be £5,120