Report for March 2018

Report Date
March 2018

Achievements

  • Container investigation work started by Development Technology. Presentation to Applications Division staff on containers arranged for Friday 13th April.

Issues

  • Industrial action resulted in booked tasks only partially being carried out. DevTech Bookings have been re-scheduled and assigned for first 2 weeks of May.

Next Steps

  • Continue with prototype build

Budget Information

  • The project spend to date is 1 days with 19 days remaining budget.  
  • An additional 15 days have been assigned or requested, the total expected spend will be £5,120
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Container Based Service Delivery
Code
API030
Programme
Z. IS Innovation - Applications (API) - Closed
Management Office
ISG PMO
Project Manager
Peter Jackson
Project Sponsor
Jennifer Milne
Current Stage
Close
Status
Closed
Start Date
08-Jan-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Mar-2019
Overall Priority
Normal

Documentation