Report for May 2018

Report Date
May 2018

Achievements

  • Presentation to Applications Division staff rescheduled for Friday 11th June.
  • Booking assigned for developer in early June.

Issues

  • DevTech resource availability remains an potential issue, bookings have been assigned so this should be ok. 

Next Steps

  • Continue with prototype build

Budget Information

  • The project spend to date is 4 days with 16 days remaining budget.  
  • An additional 15 days have been assigned or requested, the total expected spend will be £5,120
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Container Based Service Delivery
Code
API030
Programme
Z. IS Innovation - Applications (API) - Closed
Management Office
ISG PMO
Project Manager
Peter Jackson
Project Sponsor
Jennifer Milne
Current Stage
Close
Status
Closed
Start Date
08-Jan-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Mar-2019
Overall Priority
Normal

Documentation