- Report Date
- July 2018
Achievements
- Presentation made to Applications Division technical staff giving an overview of Container technology and how we use it in the future .
- Proof of concept application developed by Development Team
Issues
- DevTech resource availability was challenging in June & July especially around work following an security related incident and follow up work.
Next Steps
- The prototype build is expected to be complete by Friday 3rd August
Budget Information
- The project spend to date in applied timesheets is 11 days.
- There is an additional 4 days that will be spent by the end of financial year, giving a total spend of 15 days from a budget of 20days
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
This article was published on