Organisation
Work/Task Breakdown
- JIRA Agile: Install, R&D of latest version, configuration and documentation - 14 days (12 BL, 2 AD)
- Detailed documentation of agile methodology, learning from the experience of ongoing projects in UWP and SSP - 8 days. This documentation will include roles; checklists and sign-offs for various stages, guidance on project management; details on how to run an iteration; etc. (1 BL, 3 AD, 4 BA)
- Review of the documentation - 5 days
- Define QA process for reviews at the end of each agile project - 1 day (1 BL)
- Creation of further in-house training material - 6 days These materials will build on the previous training course, plus material for EDUCAUSE, and will add new material about project management. (2 BL, 4 BA)
- Delivering four training courses (covering trainer time only, including admin) - 7 days. (3.5 BL, 3.5 BA)
- Setting up a practitioner's group and preparing first meeting 2 days (2 AD)
- Project management - 2 days.(2 PM)
Resources Skills and Cost
Total Apps effort required: 45 days, comprising:
Project manager/Project sponsor - 4 days
Business Lead - 20 days
Senior Analyst/Developer - 5 days
Business Analyst - 12 days
Other (e.g. reviewers) - 4 days