A lot of rooms now. PM says we get on site on the 1st June but I suspect it july at the earliest.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2018 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Bayes Institute (DTI)
Code
AV2556
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
Stephen Dishon
Project Sponsor
Anna Stamp
Current Stage
Close
Status
Closed
Start Date
01-Jan-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Aug-2018

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.