KB-New Waddington Building Project
KB-New Waddington Building Project
Home
Projects
KB-New Waddington Building Project
Status
Monthly Report
Monthly Report
Report Date
July 2018
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Issue: Fit out scheduled for January/February 2018 but have been informed it could be later due to slippage to main programme .
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on
Aug 3, 2018
Project Info
Project
KB-New Waddington Building Project
Code
AV2696B
Programme
ISG Learning and Teaching Spaces: Estates (AV)
Management Office
ISG PMO
Project Manager
John Power
Project Sponsor
Steven Poliri
Current Stage
Close
Status
Closed
Start Date
06-Dec-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2018
Overall Priority
Normal
Category
Compliance
More project information
Documentation
Not available.