Monthly Report

Report Date
May 2017
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
EB-Roslin Institute CTLGH Alcove AV
Code
AV2702
Programme
ISG Learning and Teaching Spaces: CMVM (AV)
Management Office
ISG PMO
Project Manager
Guy Tittley
Project Sponsor
Peter Freeman
Current Stage
Close
Status
Closed
Start Date
27-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a

Documentation

Not available.